§ 39-36-5. Thermal energy network pilot project.
(a) Upon the completion of any feasibility study conducted by a utility in accordance with § 39-36-4, the relevant utility shall determine if the studied project is in fact feasible and, if so, may prepare and submit a proposal to the PUC to develop a pilot project that is consistent with the subject and results of said feasibility study.
(b) The PUC shall approve cost recovery for all just and reasonably incurred costs associated with pilot projects that the PUC determines provide a net benefit to the relevant utility’s ratepayers based on its consideration of the following factors:
(1) Greenhouse gas emissions reductions;
(2) Cost-effectiveness, including projected energy-cost savings and operations and maintenance costs over the useful life of the equipment;
(3) The degree to which the projected pilot program costs are funded by sources other than ratepayers, including by direct state support and/or by grants received by the utility in support of the project;
(4) Benefits to communities experiencing disproportionate environmental or public-health burdens; and
(5) A demonstration by the utility that non-ratepayer funding sources were explored to offset costs to ratepayers including, but not limited to, federal or state grants, financing sourced through public bonds, subsidized loans, or tax credits, pursuant to the provisions of this chapter.
(c) For the avoidance of doubt, a utility shall have no obligation to proceed with a pilot project unless said project has been:
(1) Approved by the PUC; and
(2) The PUC has approved full cost recovery for the project other than to the extent such costs are funded by direct state support or by grants received by the utility in support of the project.
(d) Notwithstanding any other provision of law, any public utility engaged in the business of natural gas distribution shall, subject to approval by the public utilities commission, be entitled to own, construct, or operate thermal energy networks for the purpose of selling and distributing thermal energy and shall be entitled to charge and collect payment from its customers in connection therewith in accordance with and subject to the provisions of title 39. Nothing in this subsection shall be construed to limit the authority of the state, municipalities, cooperatives, or nonprofit entities to develop thermal energy networks in partnership with a public utility.
History of Section.
P.L. 2026, ch. 339, § 1, effective June 24, 2026; P.L. 2026, ch. 340, § 1, effective
June 24, 2026.