Title 39
Public Utilities and Carriers

Chapter 26
Renewable Energy Standard

R.I. Gen. Laws § 39-26-4.1

§ 39-26-4.1. Legislative reporting.

(a) On or before January 1, 2027, the public utilities commission shall conduct a comprehensive review of:

(1) The status of the state’s progress toward meeting the renewable energy standard;

(2) The status of the state’s progress toward meeting the greenhouse gas emissions reduction requirements;

(3) The extent to which renewable energy procurement and development within the state is sufficient to ensure long-term compliance with such requirements;

(4) The impact on meeting mandated carbon reduction goals in § 42-6.2-9;

(5) Estimated cost of compliance of the renewable energy standard; and

(6) Recommendations for creation of an intervenor compensation program to provide compensation in the form of a grant for legal fees, expert witness fees and other reasonable costs to an intervenor in public utility commission proceedings.

(b) On or before December 31, 2027, public utilities commission shall submit a report of their findings, and recommendation of actions required pursuant to this section, to the governor, the speaker of the house, the president of the senate, and the chairs of the house committees on environment and natural resources, finance, and corporations and the senate committees on finance, environment and agriculture, and commerce. The report shall detail the following:

(1) Renewable and zero-emission resources used for compliance;

(2) Estimated cost of compliance of the renewable energy standard;

(3) Impact on meeting mandated carbon reduction goals in § 42-6.2-9; and

(4) Any statutory changes needed to reach the 2033 targets established pursuant to this chapter.

History of Section.
P.L. 2026, ch. 84, art. 11, § 8, effective June 12, 2026.