2025 -- S 0981 SUBSTITUTE A AS AMENDED

========

LC002703/SUB A

========

     STATE OF RHODE ISLAND

IN GENERAL ASSEMBLY

JANUARY SESSION, A.D. 2025

____________

A N   A C T

RELATING TO STATE AFFAIRS AND GOVERNMENT -- ENERGY FACILITY SITING

ACT

     

     Introduced By: Senators Zurier, and Britto

     Date Introduced: April 16, 2025

     Referred To: Senate Housing & Municipal Government

     It is enacted by the General Assembly as follows:

1

     SECTION 1. Section 42-98-1.1 of the General Laws in Chapter 42-98 entitled "Energy

2

Facility Siting Act" is hereby amended to read as follows:

3

     42-98-1.1. Capital city underground utility initiative.

4

     (a) Legislative Findings

5

     (1) In 2004, the cities of Providence and East Providence exercised their rights under this

6

section as it was originally enacted in 2004, to forego receipt of a customer credit owed to the

7

Narragansett Electric Company’s (“company”) electric customers residing in those communities,

8

opting instead to use those communities’ allocated share of the customer credit to fund a portion of

9

the cost of constructing the “Underground Alignment” of a portion of the E-183 115 kilovolt

10

electric transmission line as defined in the Settlement Agreement approved by the Board on May

11

28, 2004 in Docket No. SB-2003-01.

12

     (2) The Settlement Agreement approved by the Board in Docket No. SB-2003-01 provided,

13

in part, that the parties to the Settlement Agreement would work to reach an agreement on a route

14

for the Underground Alignment while the Rhode Island attorney general would work to secure

15

funding for construction of the Underground Alignment. The Settlement Agreement provided

16

further that if the Underground Alignment was found not to be feasible for reasons including cost

17

or constructability, other identified alignments of the relevant portion of the E-183 electric

18

transmission line would be considered in order of preference.

 

1

     (3) On January 17, 2018, the Board issued an Order determining that the Underground

2

Alignment and the “Bridge Alignment North,” as defined in the Settlement Agreement, were not

3

feasible, and approving construction of the “Bridge Alignment South,” as defined in the Settlement

4

Agreement.

5

     (4) Following appellate review pursuant to § 42-98-12, on June 17, 2022, in Case No. 2018-

6

40-M.P., the Supreme Court of Rhode Island upheld the Board’s January 17, 2018 Order.

7

     (5) Due to the foregoing events and decisions, as of 2025, no portion of the E-183

8

transmission line has been constructed underground and no part of the customer credit referred to

9

in subsection (a)(1) of this section has been returned to electric customers in the cities of Providence

10

and East Providence.

11

     (6) The customer credit that arose from the company’s base distribution rate case in 2004,

12

which the cities of Providence and East Providence did not accept on behalf of their ratepayers, has

13

been segregated and has accrued interest for the benefit of Providence and East Providence electric

14

distribution customers.

15

     (7) The cities of Providence and East Providence desire to have portions of the E-183

16

electric transmission line located underground and require legislative authorization for funding

17

mechanisms to pay the incremental cost, over and above the estimated cost of the Bridge Alignment

18

South, of the burial of portions of the E-183 electric transmission line along the southern shore of

19

Fox and India Points that are south of Interstate 195 and in East Providence on the east side of the

20

Seekonk River (the “Bridge Alignment South – Hybrid”).

21

     (b) The public utilities commission shall permit the city of Providence or and the city of

22

East Providence, upon petition by a duly authorized representative of such municipality, to forego

23

some or apply all of the respective municipality’s pro rata share of the refund accruing to the

24

ratepayers of the respective municipality as computed under section 11(c) of the 3rd Third

25

Amended Settlement Agreement in Docket No. 2930; provided, however, that the city council of

26

each petitioning ratifies such action by passage of a resolution.

27

     (b) The public utilities commission shall permit, upon petition by the attorney general, for

28

the use of up to two million dollars ($2,000,000) from Narragansett Electric Company’s Storm

29

Contingency Fund for purposes of under grounding that portion of the E-183 transmission line

30

under consideration in Energy Facility Siting Board Docket 2003-01.

31

     (c) Narragansett Electric Company shall be required to apply to the regional grid operator

32

or its successor organization for approval to charge New England regional network service

33

customers for the capital costs associated with the construction of Phase II overhead configuration

34

labeled the “North Bridge Alignment” as defined by the Settlement Agreement that was approved

 

LC002703/SUB A - Page 2 of 6

1

by the Energy Facility Siting Board in Docket 2003-1.

2

     (d) The Narragansett Electric Company (“company”) shall be authorized to proceed with

3

the construction of the underground alignment of the E-183 line referenced in the Settlement

4

Agreement that was approved by the Energy Facility Siting Board in Docket 2003-01

5

(“Underground alignment”), including the acquisition of any property rights needed to implement

6

the underground alignment, plus accrued interest, toward the incremental cost of constructing the

7

Bridge Alignment South - Hybrid.

8

     (c) The Company shall apply to the regional grid operator or its successor organization for

9

approval to charge New England regional network service customers for the capital costs associated

10

with undergrounding portions of the E-183 transmission line as described herein and as verified for

11

feasibility by the Narragansett Electric Company. Any Portion of costs not categorized as eligible

12

for regional cost allocation shall be governed by subsections (d) through (f) of this section and

13

remain chargeable to the electric customers of Providence and East Providence.

14

     (d) Notwithstanding the Supreme Court’s June 17, 2022 affirmation of the Board’s January

15

17, 2018 Order, the Board shall have jurisdiction to consider a modification to the license to include

16

burial of a portion of the E-183 electric transmission line without having to consider whether the

17

requirements of §§ 42-98-11(b)(1) and (b)(2) have been met. Following approval by the Board of

18

a modified license, the company shall be authorized to proceed with the construction of the

19

modification which will include consideration of the Bridge Alignment South-Hybrid, subject to

20

the passage of resolutions by both city councils of the cities of Providence and East Providence

21

agreeing that any incremental costs above existing funding made available pursuant to subsection

22

(b) of this section may be included in electric rates of electric customers in those cities. Such

23

resolutions must be delivered to the public utilities commission no later than July 1, 2009.

24

Notwithstanding the terms of the Settlement, to 2026. To the extent the actual costs for the

25

underground alignment Bridge Alignment South - Hybrid exceed the funding obtained for the

26

project pursuant to this section and from federal and any other sources, the company is authorized

27

to include the incremental costs above those funding levels in its distribution rate base and reflect

28

the revenue requirement, including interest, any resulting tax adjustments, and billing system

29

modification costs in rates charged to the electric distribution customers within the cities of

30

Providence and East Providence in a manner approved by the public utilities commission, subject

31

to the timely passage and delivery of the resolution resolutions specified above. Such rate

32

adjustment shall be made within six (6) months from project completion, applying the same

33

ratemaking principles as ordinarily applied to distribution capital projects when they are allowed

34

in its distribution rate base by the public utilities commission. After completion of the underground

 

LC002703/SUB A - Page 3 of 6

1

alignment, the public utilities commission shall conduct a review of costs incurred to construct the

2

underground alignment in order to verify that the company’s calculation and implementation of

3

rates are in compliance with this section; provided, further, the auditor general shall perform a

4

performance audit of state costs. billed as a per kilowatt hour charge designed to recover the full

5

incremental cost of the Bridge Alignment South – Hybrid, including interest, any resulting tax

6

adjustments, and billing system modification costs, over a period not less than three (3) years

7

subject to reconciliation of the final cost compared to billed revenues. The incremental costs of

8

undergrounding net of the customer credit referenced in subsection (b) of this section will be

9

allocated to each city based on the actual cost of the underground portions in each respective city.

10

The company shall book the revenues collected through the rate adjustment for such incremental

11

underground construction costs as contribution in aid of construction in the appropriate

12

transmission accounts.

13

     (e) If the cities of Providence and East Providence obtain any other source of funding that

14

can be used to offset the cost of burial of the E-183 electric transmission line, that source of funding

15

shall offset the amount of the rate adjustment charged to the electric ratepayers in the cities of

16

Providence and/or East Providence under subsection (c) of this section as defined by the source of

17

funding.

18

     (e)(f) If the underground alignment goes forward, the company shall retain such portions

19

of the properties acquired to implement the underground alignment as may be necessary and

20

prudent, and shall transfer any remaining portions of said properties to the redevelopment authority

21

of the city in which the property is located after the completion of the project, at the city’s request

22

and at no additional cost to the city conditions precedent to the construction of the Bridge

23

Alignment South - Hybrid are satisfied, the cities of Providence and East Providence shall acquire

24

and convey to the company, all easements or property rights needed in the company’s reasonable

25

judgment for the construction, operation, and maintenance of the relevant segment of E-183. Any

26

costs associated with the transfer of property rights will be included in the overall project costs and

27

allocated as described in subsection (d) of this section. Any property and easements no longer being

28

used by the company for utility purposes after the underground alignment Bridge Alignment South-

29

Hybrid is completed also shall be transferred to the city in which such property is located after the

30

completion of the project, at the city’s request and at no additional cost to the city. If there is any

31

dispute about the extent to which property or easements are needed and therefore should not be

32

transferred, the public utilities commission shall decide the issue upon petition by the affected city.

33

     SECTION 2. This act shall take effect upon passage.

 

LC002703/SUB A - Page 4 of 6

========

LC002703/SUB A

========

 

LC002703/SUB A - Page 5 of 6

EXPLANATION

BY THE LEGISLATIVE COUNCIL

OF

A N   A C T

RELATING TO STATE AFFAIRS AND GOVERNMENT -- ENERGY FACILITY SITING

ACT

***

1

     This act would allow for measures to advance the undergrounding of certain utility cables

2

and to have the same funded through utility rate increases to the cities of Providence and East

3

Providence.

4

     This act would take effect upon passage.

========

LC002703/SUB A

========

 

LC002703/SUB A - Page 6 of 6