2025 -- H 6203

========

LC002551

========

     STATE OF RHODE ISLAND

IN GENERAL ASSEMBLY

JANUARY SESSION, A.D. 2025

____________

A N   A C T

RELATING TO PUBLIC UTILITIES AND CARRIERS -- THE RENEWABLE ENERGY

GROWTH PROGRAM

     

     Introduced By: Representatives Chippendale, J. Brien, Paplauskas, Quattrocchi,
Santucci, Newberry, Place, Fascia, Nardone, and Hopkins

     Date Introduced: April 09, 2025

     Referred To: House Corporations

     It is enacted by the General Assembly as follows:

1

     SECTION 1. Chapter 39-26.6 of the General Laws entitled "The Renewable Energy

2

Growth Program" is hereby repealed in its entirety.

3

CHAPTER 39-26.6

4

The Renewable Energy Growth Program

5

     39-26.6-1. Purpose.

6

     The purpose of this chapter is to enable the state to meet its climate and resilience goals,

7

including those established in the act on climate. This includes the goals to facilitate and promote

8

installation of grid-connected generation of renewable energy; support and encourage development

9

of distributed renewable energy generation systems while protecting important core forest areas

10

essential to climate resilience and complying with Rhode Island’s climate change mandates; reduce

11

environmental impacts; reduce carbon emissions that contribute to climate change by encouraging

12

the siting of renewable energy projects in the load zone of the electric distribution company and in

13

preferred areas that have already been disturbed by industry or other uses; diversify the energy-

14

generation sources within the load zone of the electric distribution company; stimulate economic

15

development; and improve distribution-system resilience and reliability within the load zone of the

16

electric distribution company.

17

     39-26.6-2. Renewable energy growth program established.

18

     To carry out these purposes, a tariff-based, renewable energy distributed-generation

 

1

financing program, hereinafter referred to as the renewable energy growth program, is hereby

2

established with the intention of continuing the development of renewable energy distributed

3

generation in the load zone of the electric distribution company at reasonable cost. The program

4

shall be designed to finance the development, construction, and operation of renewable energy

5

distributed-generation projects over five (5) years through a performance-based incentive system

6

that is designed to achieve specified megawatt targets at reasonable cost through competitive

7

processes. The renewable energy growth program shall be implemented by the electric distribution

8

company, and guided by the distributed-generation board, in consultation with the office of energy

9

resources, subject to the review and supervision of the commission.

10

     39-26.6-3. Definitions.

11

     When used in this chapter, the following terms shall have the following meanings:

12

     (1) “Board” shall mean the distributed-generation board as established pursuant to the

13

provisions of § 39-26.2-10 under the title distributed generation standard contract board, but shall

14

also fulfill the responsibilities set forth in this chapter.

15

     (2) “Ceiling price” means the bidding price cap(s) applicable to each annual enrollment for

16

a given distributed-generation class, that shall be approved for each renewable energy class

17

pursuant to the procedure established in this chapter. The ceiling price(s) are not required to, but

18

may be, approved for up to three years. The ceiling price for each technology should be a price that

19

would allow a private owner to invest in a given project at a reasonable rate of return, based on

20

recently reported and forecast information on the cost of capital and the cost of generation

21

equipment. The calculation of the reasonable rate of return for a project shall include, where

22

applicable, any state or federal incentives, including, but not limited to, tax incentives. Nothing

23

shall prohibit the distributed-generation board from proposing revised ceiling prices prior to a

24

program year to account for changes to available federal or state tax incentives, trade tariffs, or

25

other federal or state incentives that would affect the calculation of the rate of return on a project.

26

     (3) “Commercial-scale solar project” means a solar distributed-generation project with the

27

nameplate capacity specified in § 39-26.6-7.

28

     (4) “Commission” means the Rhode Island public utilities commission.

29

     (5) “Community remote distributed-generation system” means a distributed-generation

30

facility greater than two hundred fifty kilowatt (250 KW) nameplate direct current that allocates

31

bill credits for each kilowatt hour (KWh) generated to a minimum of three (3), eligible recipient-

32

customer accounts, provided that no more than fifty percent (50%) of the credits produced by the

33

system are allocated to one eligible recipient-customer account, and provided further that at least

34

fifty percent (50%) of the credits produced by the system are allocated to eligible recipients in an

 

LC002551 - Page 2 of 24

1

amount not to exceed that which is produced annually by twenty-five kilowatt (25 KW) AC

2

capacity. The community remote distributed-generation system may transfer credits to eligible

3

recipient-customer accounts in an amount that is equal to, or less than, the sum of the usage of the

4

eligible recipient-customer accounts measured by the three-year-average (3) annual consumption

5

of energy over the previous three (3) years. A projected, annual consumption of energy may be

6

used until the actual three-year-average (3) annual consumption of energy over the previous three

7

(3) years at the eligible recipient-customer accounts becomes available for use in determining

8

eligibility of the generating system. The community remote distributed-generation system may be

9

owned by the same entity that is the customer of record on the net-metered account or may be

10

owned by a third party.

11

     (6) “Core forest” refers to unfragmented forest blocks of single or multiple parcels totaling

12

two hundred fifty (250) acres or greater unbroken by development and at least twenty-five (25)

13

yards from mapped roads, with eligibility questions to be resolved by the director of the department

14

of environmental management. Such determination shall constitute a contested case as defined in

15

§ 42-35-1. Notwithstanding any other provisions of this chapter, no renewable-distributed-

16

generation project that is located or planned to be located in or on a core forest, shall be considered

17

an eligible renewable-distributed-generation project or otherwise be eligible to participate in this

18

program, unless it is on a preferred site.

19

     (7) “Distributed-generation facility” means an electrical-generation facility located in the

20

electric distribution company’s load zone with a nameplate capacity no greater than five megawatts

21

(5 MW), except for solar projects as described in § 39-26.6-7 that may exceed five megawatts (5

22

MW) but shall not be greater than fifteen megawatts (15 MW), unless located on preferred sites, in

23

which case they may be sized up to thirty-nine megawatts (39 MW), using eligible renewable

24

energy resources as defined by § 39-26-5, including biogas created as a result of anaerobic

25

digestion, but, specifically excluding all other listed eligible biomass fuels, and connected to an

26

electrical power system owned, controlled, or operated by the electric distribution company. For

27

facilities developed in core forests on preferred sites, no more than one hundred thousand square

28

feet (100,000 sq. ft.) of core forest shall be removed, except for work required for utility

29

interconnection or development of a brownfield, in which case no more core forest than necessary

30

for interconnection or brownfield development shall be removed. For purposes of this chapter, a

31

distributed-generation facility must be a new resource that:

32

     (i) Has not begun operation;

33

     (ii) Is not under construction, but excluding preparatory site work that is less than twenty-

34

five percent (25%) of the estimated total project cost; and

 

LC002551 - Page 3 of 24

1

     (iii) Except for small-scale solar projects, does not have in place investment or lending

2

agreements necessary to finance the construction of the facility prior to the submittal of an

3

application or bid for which the payment of performance-based incentives is sought under this

4

chapter except to the extent that such financing agreements are conditioned upon the project owner

5

being awarded performance-based incentives under the provisions of this chapter. For purposes of

6

this definition, preexisting hydro generation shall be exempt from the provisions of subsection

7

(7)(i) regarding operation, if the hydro-generation facility will need a material investment to restore

8

or maintain reliable and efficient operation and meet all regulatory, environmental, or operational

9

requirements. For purposes of this provision, “material investment” shall mean investment

10

necessary to allow the project to qualify as a new, renewable energy resource under § 39-26-2. To

11

be eligible for this exemption, the hydro-project developer at the time of submitting a bid in the

12

applicable procurement must provide reasonable evidence with its bid application showing the level

13

of investment needed, along with any other facts that support a finding that the investment is

14

material, the determination of which shall be a part of the bid review process set forth in § 39-26.6-

15

16 for the award of bids.

16

     (8) “Distributed-generation project” means a distinct installation of a distributed-

17

generation facility. An installation will be considered distinct if it does not violate the segmentation

18

prohibition set forth in § 39-26.6-9.

19

     (9) “Electric distribution company” means a company defined in § 39-1-2(a)(12),

20

supplying standard-offer service, last-resort service, or any successor service to end-use customers,

21

but not including the Block Island Power Company or the Pascoag Utility District.

22

     (10) “ISO-NE” means Independent System Operator-New England, the Regional

23

Transmission Organization for New England designated by the Federal Energy Regulatory

24

Commission.

25

     (11) “Large distributed-generation project” means a distributed-generation project that has

26

a nameplate capacity that exceeds the size of a small distributed-generation project in a given year,

27

but is no greater than five megawatts (5 MW) nameplate capacity.

28

     (12) “Large-scale solar project” means a solar distributed-generation project with the

29

nameplate capacity specified in § 39-26.6-7.

30

     (13) “Medium-scale solar project” means a solar distributed-generation project with the

31

nameplate capacity specified in § 39-26.6-7.

32

     (14) “Office” means the Rhode Island office of energy resources.

33

     (15) “Preferred sites” means a location for a renewable energy system that has had prior

34

development, including, but not limited to: landfills, gravel pits and quarries, highway and major

 

LC002551 - Page 4 of 24

1

road median strips, brownfields, superfund sites, parking lots or sites that are designated

2

appropriate for carports, and all rooftops including, but not limited to, residential, commercial,

3

industrial and municipal buildings.

4

     (16) “Program year” means a year beginning April 1 and ending March 31, except for the

5

first program year, that may commence after April 1, 2015, subject to commission approval.

6

     (17) “Renewable energy certificate” means a New England Generation Information System

7

renewable energy certificate as defined in § 39-26-2(14).

8

     (18) “Renewable energy classes” means categories for different renewable energy

9

technologies using eligible renewable energy resources as defined by § 39-26-5, including biogas

10

created as a result of anaerobic digestion, but, specifically excluding all other listed eligible biomass

11

fuels specified in § 39-26-2(6). For each program year, in addition to the classes of solar distributed

12

generation specified in § 39-26.6-7, the board shall determine the renewable energy classes as are

13

reasonably feasible for use in meeting distributed-generation objectives from renewable energy

14

resources and are consistent with the goal of meeting the annual target for the program year. The

15

board may make recommendations to the commission to add, eliminate, or adjust renewable energy

16

classes for each program year, provided that the solar classifications set forth in § 39-26.6-7 shall

17

remain in effect for at least the first two (2) program years and no distributed-generation project

18

may exceed five megawatts (5 MW) of nameplate capacity except for solar projects as described

19

in § 39-26.6-7.

20

     (19) “Shared solar facility” means a single small-scale or medium-scale solar facility that

21

must allocate bill credits to at least two (2), and no more than fifty (50), accounts in the same

22

customer class and on the same or adjacent parcels of land. Public entities may allocate such bill

23

credits to at least two (2), and up to fifty (50), accounts without regard to physical location so long

24

as the facility and accounts are within the same municipality. In no case will the annual allocated

25

credits in KWh exceed the prior three-year (3) annual average usage, less any reductions for verified

26

energy-efficiency measures installed at the customer premises, of the customer account to which

27

the bill credits are transferred.

28

     (20) “Small distributed-generation project” means a distributed-generation renewable

29

energy project that has a nameplate capacity within the following: Wind: fifty kilowatts (50 KW)

30

to one and one-half megawatts (1.5 MW); small-scale solar projects and medium-scale solar

31

projects with the capacity limits as specified in § 39-26.6-7. For technologies other than solar and

32

wind, the board shall set the nameplate capacity-size limits, but such limits may not exceed one

33

megawatt (1 MW).

34

     (21) “Small-scale solar project” means a solar distributed-generation project with the

 

LC002551 - Page 5 of 24

1

nameplate capacity specified in § 39-26.6-7.

2

     39-26.6-4. Continuation of board.

3

     (a) The distributed generation standard contract board shall remain fully constituted and

4

authorized as provided in chapter 26.2 of this title; provided, however, that the name shall be

5

changed to the “distributed-generation board.” Additional purposes of the board shall be to:

6

     (1) Evaluate and make recommendations to the commission regarding ceiling prices and

7

annual targets, the make-up of renewable energy classifications eligible under the distributed-

8

generation growth program, the terms of the tariffs, and other duties as set forth in this chapter;

9

     (2) Provide consistent, comprehensive, informed, and publicly accountable involvement

10

by representatives of all interested stakeholders affected by, involved with, or knowledgeable about

11

the development of distributed-generation projects that are eligible for performance-based

12

incentives under the distributed-generation growth program; and

13

     (3) Monitor and evaluate the effectiveness of the distributed-generation growth program.

14

     (b) The office, in consultation with the board, shall be authorized to hire, or to request the

15

electric distribution company to hire, the services of qualified consultants to perform ceiling price

16

studies subject to commission approval that shall be granted or denied within sixty (60) days of

17

receipt of such request from the office. The cost of the studies shall be recoverable through the rate-

18

reconciliation provisions of the electric distribution company set forth in § 39-26.6-25, subject to

19

commission approval. In addition, the office, in consultation with the board, may request the

20

commission to approve other costs incurred by the board, office, or the electric distribution

21

company to utilize consultants for annual programmatic services or to perform any other studies

22

and reports, subject to the review and approval of the commission, that shall be granted or denied

23

within one hundred twenty (120) days of receipt of the request from the office, and that shall be

24

recoverable through the same reconciliation provisions.

25

     (c) Revenues generated through the rate reconciliation process to finance the expenses

26

incurred as outlined in subsection (b) shall be transferred to the office and deposited in a restricted-

27

receipt account within the general fund. The restricted-receipt account shall be exempt from the

28

indirect cost recovery assessment under § 35-4-27.

29

     39-26.6-5. Tariffs proposed and approved.

30

     (a) Each year the electric distribution company shall file tariffs with the commission that

31

are designed to provide a multiyear stream of performance-based incentives to eligible renewable-

32

distributed-generation projects for a term of years, under terms and conditions set forth in the tariffs

33

and approved by the commission. The tariffs shall set forth the rights and obligations of the owner

34

of the distributed-generation project and the conditions upon which payment of performance-based

 

LC002551 - Page 6 of 24

1

incentives by the electric distribution company will be paid. The tariffs shall include the non-price

2

conditions set forth in §§ 39-26.2-7(2)(i) — (vii) for small distributed-generation projects (other

3

than small- and medium-scale solar) and large distributed-generation projects; provided, however,

4

that the time periods for the projects to reach ninety percent (90%) of output shall be extended to

5

twenty-four (24) months (other than eligible anaerobic-digestion projects, which shall be thirty-six

6

(36) months, and eligible small-scale hydro, and large-scale solar projects which shall be forty-

7

eight (48) months). The non-price conditions in the tariffs for small- and medium-scale solar shall

8

take into account the different circumstances for distributed-generation projects of the smaller sizes.

9

     (b) In addition to the tariff(s), the filing shall include the rules governing the solicitation

10

and enrollment process. The solicitation rules will be designed to ensure the orderly functioning of

11

the distributed-generation growth program and shall be consistent with the legislative purposes of

12

this chapter.

13

     (c) In proposing the tariff(s) and solicitation rules applicable to each year, the tariff(s) and

14

rules shall be developed by the electric distribution company and will be reviewed by the office

15

and the board before being sent to the commission for its approval. The proposed tariffs shall

16

include the ceiling prices and term lengths for each tariff that are recommended by the board. The

17

term lengths shall be from fifteen (15) to twenty (20) years; provided, however, that the board may

18

recommend shorter terms for small-scale solar projects. Whatever term lengths between fifteen

19

(15) and twenty (20) years are chosen for any given tariff, the evaluation of the bids for that tariff

20

shall be done on a consistent basis such that the same term lengths for competing bids are used to

21

determine the winning bids.

22

     (d) In setting the ceiling prices, the board may specifically consider:

23

     (1) Transactions for newly developed renewable energy resources, by technology and size,

24

in the ISO-NE control area and the northeast corridor;

25

     (2) Pricing from bids received during the previous program year;

26

     (3) Environmental benefits, including, but not limited to, reducing carbon emissions;

27

     (4) For community remote distributed-generation systems, administrative costs and

28

financial benefits for participating customers;

29

     (5) System benefits;

30

     (6) Cost-effectiveness;

31

     (7) Location of projects, including climate resilience and conservation benefits; and

32

     (8) Labor standards pursuant to chapter 26.9 of this title.

33

     (e) At least forty-five (45) days before filing the tariff(s) and solicitation rules, the electric

34

distribution company shall provide the tariff(s) and rules in draft form to the board for review. The

 

LC002551 - Page 7 of 24

1

commission shall have the authority to determine the final terms and conditions in the tariff and

2

rules. Once approved, the commission shall retain exclusive jurisdiction over the performance-

3

based incentive payments, terms, conditions, rights, enforcement, and implementation of the tariffs

4

and rules, subject to appeals pursuant to chapter 5 of this title.

5

     39-26.6-6. Permanence of tariff terms once set.

6

     It is the intention of the general assembly in enacting this chapter that the developers,

7

owners, investors, customers, and lenders of the distributed-generation projects receiving

8

performance-based incentives under the tariffs be able to rely on the tariffs for the entire term of

9

the applicable tariff for purposes of obtaining financing. Consistent with that intention and

10

expectation, the terms under the tariffs for a given program year, once approved by the commission,

11

shall not be altered in any way that would undermine such reliance on those tariffs during the

12

applicable terms of the tariffs; and in no circumstance will the performance-based incentive rate

13

paid to a renewable energy project developer or owner be reduced during the term of the tariff once

14

a renewable energy project has qualified to receive a tariff under the terms of this chapter.

15

     39-26.6-7. Solar project size categories.

16

     (a) Tariff(s) shall be proposed for each of the following solar distributed-generation

17

classes:

18

     (1) Small-scale solar projects;

19

     (2) Medium-scale solar projects;

20

     (3) Commercial-scale solar projects; and

21

     (4) Large-scale solar projects.

22

     (b) Such classes of solar distributed-generation projects shall be established based on

23

nameplate megawatt size as follows:

24

     (1) Large-scale solar projects shall be comprised of four (4) classes as follows:

25

     (i) One megawatt (1 MW) but less than five megawatts (5 MW), nameplate capacity;

26

     (ii) Five megawatts (5 MW), but less than ten megawatts (10 MW), nameplate capacity;

27

     (iii) Ten megawatts (10 MW), but less than fifteen megawatts (15 MW), nameplate

28

capacity; and

29

     (iv) Fifteen megawatts (15 MW), but less than thirty-nine megawatts (39 MW), nameplate

30

capacity for projects located on preferred sites;

31

     (2) Commercial scale shall be comprised of solar projects greater than two hundred fifty

32

kilowatts (250 KW), but less than one megawatt (1 MW) nameplate capacity;

33

     (3) Medium scale shall be comprised of solar projects greater than twenty-five kilowatts

34

(25 KW), up to and including, two hundred fifty kilowatts (250 KW) nameplate capacity; and

 

LC002551 - Page 8 of 24

1

     (4) Small scale shall be comprised of solar projects up to and including twenty-five

2

kilowatts (25 KW) nameplate capacity.

3

     (c) Other classifications of solar projects may also be proposed by the board, subject to the

4

approval of the commission. After the second program year, the board may make recommendations

5

to the commission to adjust the size categories of the solar classes, provided that the medium-scale

6

solar projects may not exceed two hundred fifty kilowatts (250 KW); and/or allocated capacity to

7

community distributed-generation facilities, allowing them to compete or enroll under a distinct

8

ceiling price.

9

     39-26.6-8. Renewable technologies other than solar.

10

     Tariffs also shall be proposed for on-shore wind and any other distributed-generation

11

technologies permissible under this chapter that the board, in its discretion, recommends; provided,

12

however, that no project shall exceed five megawatts (5 MW) nameplate capacity. The electric

13

distribution company shall file tariffs for each technology and size categories recommended by the

14

board pursuant to the procedures set forth in this chapter.

15

     39-26.6-9. Project segmentation prohibition.

16

     In no case may a project developer be allowed to segment a distributed-generation project

17

on the same parcel or contiguous parcels into smaller-sized projects in order to fall under a smaller-

18

size project classification. Notwithstanding this prohibition, a project developer may designate a

19

generation unit on the same parcel or contiguous parcel for net metering or other means of

20

participating in electricity markets, provided that the unit, or portion of the unit, designated for net

21

metering or other market participation is not receiving performance-based incentives under this

22

chapter; is capable of being segregated electrically; is configured with the electrical segregation;

23

and is separately metered. Further, a project shall not be considered to have been segmented if:

24

     (1) There is a lapse of at least twenty-four (24) months between: (i) The commencement

25

of construction of new distributed-generation units on a parcel that is the same as, or is contiguous

26

with, a parcel upon which a distributed-generation project has already been constructed; and (ii)

27

The operation date of the preexisting project; or

28

     (2) The new project is a different renewable technology.

29

     39-26.6-10. Timing and schedule of tariff filings.

30

     (a) The electric distribution company shall file with the commission the first set of tariffs

31

and solicitation rules pursuant to this chapter no later than November 15, 2014. Thereafter, the

32

electric distribution company shall make tariff and solicitation rules filings with the commission

33

no later than November 15 prior to the beginning of the applicable program year when necessary,

34

which tariffs and rules shall be applicable for the next program year(s).

 

LC002551 - Page 9 of 24

1

     (b) Upon receiving the filing from the electric distribution company, the commission shall

2

open a docket to consider the filing. The commission shall issue an order approving the proposed

3

tariffs and solicitation rules; provided, however, that the commission may make any modifications

4

that it deems appropriate consistent with the legislative purposes of this chapter as set forth herein.

5

     (c) The commission shall approve tariff(s) and solicitation rules prior to the

6

commencement of the applicable year(s).

7

     (d) During the course of any program year, the electric distribution company may, at any

8

time, in consultation with the office and the board, propose tariff or solicitation rules modifications.

9

The commission shall consider the proposed modifications through an already open or new docket,

10

and shall issue its order within one hundred five (105) days of the filing of the proposed

11

modification. If approved, the proposed modification shall take effect for the next enrollment event

12

following the issuance of the commission’s order.

13

     39-26.6-11. Power purchase agreements not required.

14

     The distributed-generation growth program shall be implemented and administered

15

exclusively through the tariff structure and procedures set forth in this chapter, and the electric

16

distribution company shall not be required to execute power purchase agreements for the

17

procurement of the renewable energy distributed-generation capacity requirements set forth in this

18

chapter.

19

     39-26.6-12. Annual bidding and enrollments.

20

     (a) The electric distribution company, in consultation with the board and office, shall

21

conduct at least three (3) tariff enrollments for each distributed-generation class each program year.

22

     (b) During each program year, the tariff enrollments shall have both an annual targeted

23

amount of nameplate megawatts (“annual MW target”) and a nameplate megawatt target for each

24

separate enrollment event (“enrollment MW target”). The enrollment MW target shall comprise the

25

specific portion of the annual MW target sought to be obtained in that enrollment. The annual MW

26

target(s) and enrollment MW targets shall be recommended by the board no less frequently than

27

every three (3) years, subject to commission approval. The board shall also recommend a megawatt

28

target for each class (“class MW target”) that comprises a specified portion of the enrollment MW

29

target, subject to commission approval. If the electric distribution company, the office, and the

30

board mutually agree, they may reallocate megawatts during an enrollment from one class to

31

another without commission approval if there is an over-subscription in one class and an under-

32

subscription in another, provided that the annual MW target is not being exceeded, except as

33

provided in § 39-26.6-17. No reallocation of megawatts from a competitive pricing class to a non-

34

competitive pricing class shall be made until after the completion of the three (3) enrollment periods

 

LC002551 - Page 10 of 24

1

in the program year and in no case may the annual MW target be exceeded as a result of a

2

reallocation of megawatts.

3

     (c) The annual MW targets shall be established from the year 2023 through the year 2033.

4

The annual target for each program year shall be up to three hundred megawatts (300 MW);

5

provided that, thirty megawatts (30 MW) shall be reserved for projects less than one megawatt (1

6

MW). The board may petition the commission for approval of multi-year annual targets and

7

associated-ceiling prices.

8

     (d) – (j) [Deleted by P.L. 2023, ch. 300, § 2 and P.L. 2023, ch. 301, § 2.]

9

     39-26.6-13. Cost reconciliation.

10

     To the extent the electric distribution company incurs incremental costs to meet the

11

program objectives or make billing system improvements that are required to facilitate payments

12

of performance-based incentives and administering net metering, the electric distribution company

13

may elect to recover those incremental costs through the annual charge set forth in § 39-26.6-25,

14

subject to commission review and approval that assures such costs were properly and prudently

15

incurred.

16

     39-26.6-14. Existing powers of agencies and advocacy rights of parties unchanged.

17

     Nothing in this chapter shall be construed to derogate from the statutory authority of the

18

commission or the division of public utilities and carriers, including, but not limited to, the authority

19

to protect ratepayers from unreasonable rates. Nothing in this chapter shall be construed to preclude

20

any party from advocating a position in commission proceedings that differs from the

21

recommendations made by the board to the commission or in any filing with the commission

22

relating to this chapter, including, without limitation: (1) Individual or organizational members of

23

the board; (2) Participants in board deliberations; (3) The office; and (4) The electric distribution

24

company, unless the party has consented by vote to the execution or executed a settlement

25

agreement agreeing to the terms, policy proposals, or any other matter proposed to the commission.

26

     39-26.6-15. Bidding and incentive award processes for solar DG projects.

27

     (a) Large-scale and commercial-scale solar projects and distributed-generation projects for

28

other eligible technologies shall bid a price-per-kilowatt-hour for the entire output of the facility

29

(net of any station service) that shall not exceed the applicable ceiling price. Small-scale and

30

medium-scale solar projects will submit an enrollment application to receive a standard

31

performance-based incentive for the period of years in the applicable tariff, that shall be a price-

32

per-kilowatt-hour for the entire output of the facility. Except for megawatts that may be allocated

33

to the energy-efficiency program pursuant to § 39-26.6-19, small- and medium-scale projects shall

34

be selected on a first-come, first-served basis, or by means of a commission-approved lottery

 

LC002551 - Page 11 of 24

1

system, or such other method as may be recommended by the board and approved by the

2

commission.

3

     (b) Except for the first program year, the board shall determine, subject to commission

4

approval, the standard performance-based incentive for small- and medium-sized solar projects

5

from the average bid price from the last two (2) procurement enrollments conducted in the

6

commercial-scale and/or large-scale solar projects class. The standard performance incentive may

7

be set at a higher rate than payments for commercial-scale and large-scale solar projects in order to

8

take into account the potentially higher per-unit cost of smaller projects. The standard performance

9

incentive also shall be adjusted upward or downward, as needed, in order to take into account the

10

term length over which the incentive shall be paid for the small- and medium-scale solar projects

11

if such terms are different than the terms applicable to the classes from which the standard

12

performance incentive was derived.

13

     (c) For each program year, the board shall recommend to the commission a standard

14

performance incentive for each of the small-scale and medium-scale solar project classifications,

15

which performance incentives may span up to three program years. Upon receiving the

16

recommendations from the board, the commission shall open a docket to consider the

17

recommendations or address the recommendations in its approval process for the applicable

18

program year(s) in a consolidated docket as provided in § 39-26.6-10. The commission shall issue

19

its order approving the recommendations no later than concurrently with approval of the entire

20

program and tariffs applicable to the program year; provided, however, that the commission may

21

make modifications or changes to the board’s recommendations consistent with the legislative

22

purposes of this chapter.

23

     (d) If after the first program year, the applications for the medium-scale solar projects are

24

significantly over-subscribed, then the board and the electric distribution company, in consultation

25

with the office, may propose to the commission a bidding process for medium-scale projects or a

26

subset of the medium-scale projects under which project selections would be made based on the

27

lowest bids, rather than first-come, first-served or such other method previously approved by the

28

commission. The commission shall approve the proposal from the board and electric company

29

within ninety (90) days; provided, however, that the commission may make changes to the proposal

30

consistent with the legislative purposes of this chapter.

31

     (e) The commission shall approve the bidding process for medium-scale solar projects

32

recommended by the board only if the commission finds that such bidding process is in a

33

sufficiently simple form that is not administratively burdensome to bidders, and will not have the

34

effect of discouraging participation in the distributed-generation growth program by developers of

 

LC002551 - Page 12 of 24

1

medium-scale solar projects that may be unrepresented by counsel.

2

     39-26.6-16. Enrollment program.

3

     (a) Each enrollment shall be open for a two-week (2) period during which the electric

4

distribution company is required to receive standard short-form applications. The standard short-

5

form application shall require the applicant to provide the following information: the project

6

owner’s identity; the location of the proposed project; the nameplate capacity of the proposed

7

project; and renewable energy class of the proposed project. The standard short-form application

8

shall allow project owners to provide additional information relative to the permitting, financial

9

feasibility, ability to build, and timing for deployment of the proposed projects. The applicant must

10

submit an affidavit with the standard short-form application confirming that the project is not in

11

violation of the rules that prohibit project segmentation, as set forth in § 39-26.6-9.

12

     (b) For large distributed-generation projects only, the standard short-form application shall

13

also require the applicant to bid a bundled price that applies to the energy, renewable energy

14

certificates, and all other environmental attributes and market products that are available, or may

15

become available, from the distributed-generation facility on a per-kilowatt-hour basis measured

16

from the output of the project. At the election of the electric distribution company, and subject to

17

the approval of the commission, the bid may be required to include the sale of capacity.

18

     (c) For (i) Small distributed-generation projects other than small-scale and medium-scale

19

solar projects; and (ii) Large distributed-generation projects, the electric distribution company shall

20

select projects based on the lowest proposed prices received that do not exceed the ceiling price

21

from the distributed-generation projects that meet the requirements of all applicable tariffs and

22

regulations, and meet the criteria of the renewable energy class in effect, until the class target is

23

met. Performance-based incentives shall be awarded to the winning bidders based on their bids

24

submitted.

25

     (d) For small-scale and medium-scale solar projects, awards shall be made in the manner

26

set forth in §§ 39-26.6-15 and 39-26.6-19.

27

     (e) If there are more projects bidding at the same price than the capacity that is specified

28

for a class target, the electric distribution company shall, in consultation with the board and the

29

office, select first those projects that appear to be the furthest along in development and that are

30

most likely to be deployed. Those projects that are likely to be deployed at the earliest time shall

31

be selected first. To the extent the electric distribution company is unable to make a clear distinction

32

on this basis, the electric distribution company shall report its findings to the board and not award

33

bids for those projects that are tied on pricing. In that case, the board may take such action as it

34

deems appropriate for the selection of projects, including seeking more information from the

 

LC002551 - Page 13 of 24

1

projects.

2

     (f) Should the electric distribution company determine that it has made sufficient awards

3

to achieve a program-year class target, it shall immediately report this fact to the board, the office,

4

and the commission, and may cease making awards for that renewable energy class for the

5

remainder of the program year. In any event, the electric distribution company may exceed the

6

renewable energy class target if the last award may cause the total purchased to exceed the target.

7

     (g) The board, the office, and the electric distribution company shall enter into a

8

memorandum of understanding regarding the sharing of the information and data related to the

9

renewable energy growth program, including, without limitation, information on bids received,

10

details regarding project ownership, and pricing. At the request of the board, the office, or the

11

electric distribution company, the commission shall have the authority to protect from public

12

disclosure individual bid information for any projects that have not been awarded performance-

13

based incentives.

14

     (h) The electric distribution company is authorized to award bids up to the applicable

15

ceiling price. As long as the terms of the tariff are met, and the pricing is no higher than the

16

applicable ceiling price, such awards shall be deemed prudent and approved by the commission for

17

purposes of recovering the costs in rates.

18

     (i) With respect to any procurement that includes bids from pre-existing, hydroelectric

19

generation, the electric distribution company, in consultation with the office, shall have the

20

authority to accept the applicant’s representation that its investment is material, within the meaning

21

of § 39-26.6-3(7). However, if the electric distribution company or the office questions whether the

22

material investment standard has been met or the application is otherwise rejected, the application

23

shall be submitted to the board for review and the board shall draw its own conclusion and make a

24

recommendation to the commission at the time the commission is approving awards from the

25

procurement to which the application pertains. The commission shall have the final authority to

26

make the determination as to whether the material investment standard has been met. Nothing in

27

this subsection shall preclude a project developer from seeking a preliminary confirmation of

28

eligibility for the material-investment exemption from the electric distribution company, the office,

29

and the board prior to the submittal of a bid. In such case, if there is any disagreement, the final

30

determination shall be submitted to the commission.

31

     39-26.6-17. Excess enrollment not required.

32

     The electric distribution company shall not be required to award bids in excess of the

33

annual target for the applicable program year and shall not be required to procure projects in excess

34

of any limit set by the board and approved by the commission for a given enrollment. However,

 

LC002551 - Page 14 of 24

1

the electric distribution company, in consultation with the board and the office, may voluntarily

2

exceed an enrollment period limit as long as it does not exceed an annual target for the applicable

3

program year. At its election, the electric distribution company may exceed an annual target for the

4

applicable program year after review by the board and approval by the commission.

5

     39-26.6-18. Utility right to separately meter.

6

     Owners of medium-scale, commercial-scale, and large-scale solar projects and other

7

distributed-generation technologies shall be required to provide, at their cost, a revenue-quality

8

meter to standards approved by the division of public utilities and carriers and provide access to

9

the information from the meter to the electric distribution company to measure the output of the

10

generation. The electric distribution company shall have the discretion to install the second meter

11

in a parallel configuration to the retail meter or behind the meter, provided that a parallel installation

12

shall have no effect on the right of the customer to net meter using the net of the two meters. The

13

electric distribution company also shall have the right to install its own revenue-quality meter for

14

small-scale solar projects if not being supplied by the owner. The electric distribution company

15

shall recover the installation and capital cost of the separate meters it installs for small-scale solar

16

projects in the annual reconciliation of solar costs under § 39-26.6-25.

17

     39-26.6-19. Coordination with energy-efficiency programs.

18

     (a) In consultation with the office, the electric distribution company may make a request to

19

the commission that up to half of the megawatts for the small- and medium-scale solar project

20

enrollments be allocated by the commission for selection through a process coordinated with the

21

energy-efficiency program in order that specified solar incentives may be tied with energy-

22

efficiency program incentives in order to allow the electric distribution company to implement a

23

coordinated, energy efficiency and solar program offering. In this case, the electric distribution

24

company will propose criteria for eligibility for performance-based incentives for solar that require

25

certain energy-efficiency standards be met at the customer location in order to be eligible for

26

performance-based incentives for a small-scale and/or medium-scale solar installation.

27

     (b) The electric distribution company must also include program parameters that do not

28

disrupt competition among small-scale and/or medium-scale solar developers, including, without

29

limitation, safeguards against any one, or subset of, developers in this market being given exclusive

30

rights or other market advantages over competitors. In approving the proposal, the commission

31

must find that there is no such small- and medium-solar-market disruption.

32

     (c) The commission shall approve the request of the distribution company within ninety

33

(90) days, making such modifications as it deems reasonable, provided the modifications are

34

consistent with the legislative purposes of this chapter and the state’s energy-efficiency goals.

 

LC002551 - Page 15 of 24

1

     (d) The allocation of megawatts is for implementation purposes only and shall not authorize

2

funds to be shifted from the distributed-generation growth program to energy-efficiency programs,

3

nor will implementation of the electric distribution company’s request cause a reduction of the

4

annual or cumulative capacity goals established for the distributed-generation growth program. To

5

the extent that the megawatts allocated to the energy-efficiency program pursuant to this section

6

are not committed during a program year, such uncommitted megawatts shall be allocated back to

7

the distributed-generation growth program in the following year or such year the board

8

recommends to the commission. Funding for the energy-efficiency measures that are tied to the

9

solar installations must be obtained separately from the energy-efficiency program budget funded

10

through applicable energy-efficiency charges.

11

     (e) Should the small-scale and medium-scale project classes in the renewable energy

12

growth program be oversubscribed in two (2) consecutive enrollments and there are megawatts that

13

have not been committed through the process coordinated with the energy-efficiency program after

14

the second enrollment, the board, after consultation with the office and the electric distribution

15

company, shall have the authority to move all, or a portion of, the uncommitted megawatts out of

16

the coordinated program back to the renewable energy growth program to meet the demand of the

17

oversubscription, subject to commission approval. If, in such case, the board does not exercise the

18

authority, any party may file a petition to the commission requesting action to be taken.

19

     39-26.6-20. Issuance of certificates and right to incentive payments.

20

     (a) For small-scale and medium-scale solar projects, the electric distribution company shall

21

provide certificates of eligibility to the selected projects without commission confirmation of

22

approval (“distribution company awarded certificates”), subject to the review and consent of the

23

office. The electric distribution company shall file with the commission a list of all these

24

distribution-company-awarded certificates.

25

     (b) For commercial-scale and large-scale solar, and all other distributed-generation

26

projects, the electric distribution company shall file with the commission a list of the distributed-

27

generation projects selected together with the corresponding pricing information. Within sixty (60)

28

days of receipt of the list, the commission shall issue an order awarding certificates of eligibility to

29

the distributed-generation projects (“PUC awarded certificates”).

30

     (c) Upon receipt of a PUC-awarded certificate or a distribution-company certificate, a

31

distributed-generation project shall be entitled to receive, and the electric distribution company

32

shall pay and/or credit (as applicable), the performance-based incentives for the specified term, and

33

under the terms and conditions of the applicable tariff in the manner set forth below.

34

     (d) The performance-based incentive shall be the price-per-kilowatt-hour that was bid and

 

LC002551 - Page 16 of 24

1

awarded, or established as a standard incentive, as applicable. The performance-based incentive

2

shall be applied as a price-per-kilowatt-hour for all kilowatt-hours actually produced from the

3

distributed generation (net of station service, if any) for the term of years specified in the applicable

4

tariff, less the value of any kilowatt-hour charges that were offset by any net metering (if applicable)

5

for the host customer associated with the distributed generation for the billing month; provided,

6

however, if the value of kilowatt-hour charges that otherwise would be offset by net metering in a

7

given month exceeds the total value of the performance-based incentive for the month, the customer

8

shall not be subject to any additional charge, nor receive any additional net-metering credit, for the

9

difference between the performance-based incentive value and net-metering value for the month.

10

     (e) Except as provided herein for residential small-scale solar projects, in every case where

11

a distributed-generation project can be configured for net metering, it shall be the election of the

12

owner of the generation to choose one of two (2) separate methods through which the owner will

13

be compensated for the performance-based incentive:

14

     (1) The owner is compensated solely through direct payments under the performance-based

15

incentive provisions of this chapter for the life of the tariff term with no net metering implemented;

16

or

17

     (2) The owner is compensated through a combination of direct payments and the bill credit

18

value of net metering for the life of the term of the tariff under the provisions of this chapter.

19

     (3) In the case of residential small-scale solar projects, only option (2) shall be available.

20

     (4) In either option, the total value of the performance-based incentive per-kilowatt-hour

21

is the same. An owner shall have a one-time right to switch the compensation methods after the

22

generation commences operation, provided that at least sixty (60) days’ notice is given to the

23

electric distribution company. Thereafter, any further compensation method switches shall be at

24

the sole discretion of the electric distribution company if requested again by the owner.

25

     (f) Every owner who elects the compensation method shall:

26

     (1) Receive compensation solely in the form of a check from the electric distribution

27

company, or other payment method that is mutually agreed between the electric distribution

28

company and the owner; and

29

     (2) Shall receive compensation in the form of offsets against its electricity bill from the

30

electric distribution company from net metering and the balance in the form of a check from the

31

electric distribution company, or other payment method that is mutually agreed upon between the

32

electric distribution company and the owner; provided, however, that no owner of a distributed-

33

generation project may be compensated twice for the same kilowatt hour of electricity, and that

34

every self-generator shall receive the full pecuniary benefit of its election to participate in the

 

LC002551 - Page 17 of 24

1

performance-based incentive program.

2

     (g) Every owner of a distributed-generation project that can be configured for net metering

3

that elects the first option for compensation under the provisions of subsection (e) shall become

4

eligible to net meter its output in conformity with the provisions of existing law upon the

5

completion of the full term of the applicable tariff. Nothing in this section shall preclude a customer

6

from electing not to participate in the performance-based program and electing simply to net meter

7

under the provisions of existing law; provided, however, once an election is made to participate,

8

the customer will remain subject to the performance-based tariff conditions and may not terminate

9

the arrangement without the consent of the electric distribution company.

10

     (h) As provided in § 39-26.6-9, any project developer may designate a generation unit on

11

the same parcel or contiguous parcel for net metering, provided that such unit or portion of such

12

unit designated for net metering is not receiving performance-based incentives under this chapter,

13

is capable of being segregated electrically, is configured with such electrical segregation, and is

14

separately metered.

15

     (i) All distributed-generation projects accepting certificates shall be obligated to abide by

16

all the terms and conditions of the approved, applicable tariff.

17

     39-26.6-21. Ownership of output, other attributes, and renewable energy certificates.

18

     (a) Except as provided herein for residential small-scale solar projects, distributed-

19

generation projects participating in the renewable energy growth program shall transfer to the

20

electric distribution company the rights and title to:

21

     (1) Those renewable energy certificates generated by the project during the term of the

22

applicable, performance-based incentive tariff;

23

     (2) All energy produced by the generation that is not otherwise consumed on site under a

24

net-metering arrangement; and

25

     (3) Rights to any other environmental attributes or market products that are created or

26

produced by the project; provided, however, that it shall be the election of the electric distribution

27

company whether it chooses to acquire the capacity of the distributed-generation projects under the

28

tariffs set forth in this chapter and no ceiling prices recommended by the board and approved by

29

the commission will be adjusted downward in light of the electric distribution company’s election.

30

The electric distribution company shall: (1) Sell any products acquired and credit them to the

31

reconciliation account specified in § 39-26.6-25; and/or (2) Use the products to serve customers

32

and establish a price to be credited by customers using the products based on recent and near-term

33

projections of market prices. When a generator reverts to net metering after the end of the tariff

34

term under the renewable energy growth program, the net-metering generator shall retain title to

 

LC002551 - Page 18 of 24

1

the renewable energy certificates generated by the project. In the case of residential small-scale

2

projects, title to all energy and capacity produced from the solar generation shall remain with the

3

residential customer; shall not be transferred to the electric distribution company; and shall be

4

deemed consumed by the residential customer on-site during the applicable, distribution-service

5

billing period with no sale or purchase between the residential customer and the electric distribution

6

company.

7

     (b) For the accounting purposes of the electric distribution company in treating the

8

performance-based incentives, the cost of the energy that is procured shall be the real-time market

9

price of energy and the balance of the performance-based incentive shall be attributable to the

10

purchase of environmental and any other attributes acquired. This accounting shall have no effect

11

on the total, bundled performance-based incentive to which the distributed-generation project is

12

entitled under the provisions of this chapter.

13

     39-26.6-22. Zonal and other incentive payments.

14

     In order to provide the electric distribution company and the board with the flexibility to

15

encourage distributed-generation projects to be located in designated geographical areas within its

16

load zone where there is an identifiable system benefit, reliability benefit, or cost savings to the

17

distribution system in that geographical area, or conservation benefit, or climate resilience benefit

18

in that geographical area, the electric distribution company, the board, or the office, shall propose

19

to include an incentive-payment adder to the bid price of any winning bidder that proposes a

20

distributed-generation project in the preferred sites that require remediation. The company, board,

21

or office can also propose disincentive subtractors for projects outside of preferred sites. The

22

electric distribution company also may propose other incentive payments to achieve other technical

23

or public policy objectives that provide identifiable benefits to customers. Any incentive-payment

24

adders must be approved by the commission, and shall not be counted as part of the bid price when

25

the bids are selected at an enrollment event.

26

     39-26.6-23. Intersection of distributed generation and net metering.

27

     (a) Net-metering credits for excess generation shall not be credited during the term of the

28

tariff when the distributed-generation project is receiving performance-based incentive payments

29

under the tariff. After the end of the term of the performance-based incentive tariff applicable to a

30

distributed-generation project, net-metering credits for excess generation in any given month shall

31

be credited to the net-metered account at the applicable rate allowed under the law.

32

     (b) All distributed-generation projects that had begun development prior to the date the

33

commission approves the first set of ceiling price recommendations from the board and that are in

34

operation by no later than July 1, 2016, shall be eligible to continue operation under the net-

 

LC002551 - Page 19 of 24

1

metering rules that would have been applicable to that self-generation project absent the change in

2

law set forth in this section, provided that the project does not otherwise participate in the

3

performance-based incentive program set forth in this chapter.

4

     39-26.6-24. Rate design review by the commission.

5

     (a) On or after July 1, 2015, the commission shall open a docket to consider rate design

6

and distribution cost allocation among rate classes in light of net metering and the changing

7

distribution system that is expected to include more distributed-energy resources, including, but

8

not limited to, distributed generation. The commission will determine the appropriate cost

9

responsibility and contributions to the operation, maintenance, and investment in the distribution

10

system that is relied upon by all customers, including, without limitation, non-net-metered and net-

11

metered customers. In that docket, the commission shall require the electric distribution company

12

to file a revenue-neutral allocated-cost-of-service study for all rate classes and a proposal for new

13

rates for all customers in each rate class. The electric distribution company shall use the

14

distribution-revenue requirement upon which the then-current distribution rates were set. The

15

electric distribution company may use the allocated cost of service that was filed with the

16

compliance filing from the rate case when the then-current distribution rates were set. The

17

commission may also address the rate design for the equitable recovery of costs associated with

18

energy efficiency and any renewable energy programs that are recovered in rates.

19

     (b) In establishing any new rates the commission may deem appropriate, the commission

20

shall take into account and balance the following factors:

21

     (1) The benefits of distributed-energy resources;

22

     (2) The distribution services being provided to net-metered customers when the distributed

23

generation is not producing electricity;

24

     (3) Simplicity, understandability, and transparency of rates to all customers, including non-

25

net-metered and net-metered customers;

26

     (4) Equitable ratemaking principles regarding the allocation of the costs of the distribution

27

system;

28

     (5) Cost causation principles;

29

     (6) The general assembly’s legislative purposes in creating the distributed-generation

30

growth program; and

31

     (7) Any other factors the commission deems relevant and appropriate in establishing a fair

32

rate structure. The rates shall be designed for each proposed rate class in accordance with industry-

33

standard, cost-allocation principles. The commission may consider any reasonable rate design

34

options, including without limitation, fixed charges, minimum-monthly charges, demand charges,

 

LC002551 - Page 20 of 24

1

volumetric charges, or any combination thereof, with the purpose of assuring recovery of costs

2

fairly across all rate classes.

3

     (c) The commission shall issue an order in the docket by no later than March 1, 2016. Any

4

new rates shall take effect for usage on and after April 1, 2016; provided, however, that the electric

5

distribution company may seek an extension if necessary to make the billing system changes

6

necessary to implement a new rate structure. After new, revenue-neutral rates are set in the docket

7

specified above, the commission may approve changes to the rate design in any future distribution-

8

base-rate cases when a fully allocated embedded cost-of-service study is being reviewed in the rate

9

case, subject to the principles set forth in subsection (b) of this section.

10

     39-26.6-25. Forecasted rate and reconciliation.

11

     (a) On or before November 15 of each year, the electric distribution company shall file a

12

forecast of the total amount of payments that is likely to be paid out to distributed-generation

13

projects in the coming program year within the electric distribution company’s load zone, along

14

with any costs permitted for recovery pursuant to §§ 39-26.6-4, 39-26.6-13, and 39-26.6-18. The

15

total of all forecasted payments and costs shall be aggregated, net of forecasted revenues from the

16

sale of the energy, renewable energy certificates, and any other market products from the

17

distributed-generation projects participating in the performance-based incentive program. The

18

forecasted net-aggregate amount shall be used to design a fixed monthly charge per customer to

19

recover the net forecast in rates charged to all distribution customers during the prospective

20

calendar year, which fixed charge may be different by rate class in order to reasonably and equitably

21

spread the program costs across all customer classes. The fixed rate shall stay in effect until changed

22

after the first reconciliation filing set forth below and the rate reconciliation process shall be

23

repeated annually, as set forth below. The commission, in its discretion, may move the

24

reconciliation of costs and credits under § 39-26.1-5(f) into this reconciliation in order to have one

25

reconciliation of all program costs and credits from the long-term contracting standard, distributed-

26

generation standard contracting, and renewable energy growth program.

27

     (b) Within three (3) months after the end of each program year, the electric distribution

28

company shall file a report with the public utilities commission that reconciles the total amount

29

recovered from distribution customers against the total of net payments and costs for the prior

30

program year for review and approval.

31

     39-26.6-26. Shared solar facilities.

32

     (a) In order to facilitate the adoption of solar by customers in multifamily structures,

33

campuses, multi-structure business parks, multi-tenant or multi-owner commercial facilities, and

34

public entities with multiple accounts, the electric distribution company may establish rules and

 

LC002551 - Page 21 of 24

1

tariffs for program years starting on or after April 1, 2016. The rules and tariffs will set forth the

2

requirements for eligible recipients, credit transfers, consumer protection, and other considerations

3

and terms, with input from the office, for the commission’s review and approval.

4

     (b) Shared solar facilities will receive the same ceiling price and enroll from the same

5

classes of other projects of the same size and ownership as established by the board for a given

6

program year.

7

     (c) All customer accounts receiving bill credits shall be in the same customer class and the

8

bill credit value from the shared solar facility shall be determined by the recipients’ rate class and

9

not that of the facility owner. The credit value shall be the distribution, transition, transmission, and

10

standard-offer supply rates of the bill credit recipients.

11

     (d) Any value of bill credits not transferred from the shared solar facility shall be included

12

in the total performance-based incentive, which shall be paid in accordance with the tariffs

13

established by the electric distribution company.

14

     39-26.6-27. Community remote distributed generation system.

15

     (a) In order to facilitate the adoption of participation in renewable energy projects by

16

eligible customers, the board may allocate a portion of the annual MW goal to a separate class, or

17

classes, of community remote distributed-generation systems, which may compete under separate

18

ceiling prices from non-community remote distributed-generation systems, for program years

19

starting on or after April 1, 2016.

20

     (b) Upon such allocation by the board, the electric distribution company shall establish

21

rules and tariffs for program years starting on or after April 1, 2016, which rules and tariffs will set

22

forth the requirements for eligible recipients, credit transfers, consumer protection, and other

23

considerations and terms, with input from the office, for the commission’s review and approval.

24

     (c) The value of credits to be allocated to credit recipients may be a fixed rate provided by

25

the system owner, but shall not be greater than the sum of the standard-offer service, less the

26

renewable energy standard charge or credit, and the transmission and transition rates, of the credit

27

recipient as offered by the electric distribution company in effect at the time of establishing the

28

transfer. If a fixed credit rate is not provided, the default credit will be the sum of the standard-offer

29

service, less the renewable energy standard charge or credit, and the transmission and transition

30

rates, of the credit recipient as offered by the electric distribution company in effect at the time of

31

the transfer.

32

     (d) Any credits not allocated in any month will be valued at the then-current default credit

33

rate, and deducted from the total performance-based incentive of the enrolled system.

34

     (e) Community remote distributed-generation systems shall not:

 

LC002551 - Page 22 of 24

1

     (1) Comprise more than thirty percent (30%) of the annual total of capacity available under

2

the renewable energy growth program in each year;

3

     (2) Be subject to a ceiling price that is more than fifteen percent (15%) higher than the

4

then-in-effect ceiling price for the same technology of the same size as recommended by the board

5

and approved by the commission; or

6

     (3) Transfer credits to any account in an amount that in KWh exceeds the prior three-year

7

(3) annual average usage.

8

     SECTION 2. This act shall take effect on January 1, 2026.

========

LC002551

========

 

LC002551 - Page 23 of 24

EXPLANATION

BY THE LEGISLATIVE COUNCIL

OF

A N   A C T

RELATING TO PUBLIC UTILITIES AND CARRIERS -- THE RENEWABLE ENERGY

GROWTH PROGRAM

***

1

     This act would repeal the Renewable Energy Growth Program.

2

     This act would take effect on January 1, 2026.

========

LC002551

========

 

LC002551 - Page 24 of 24