2025 -- H 6203 | |
======== | |
LC002551 | |
======== | |
STATE OF RHODE ISLAND | |
IN GENERAL ASSEMBLY | |
JANUARY SESSION, A.D. 2025 | |
____________ | |
A N A C T | |
RELATING TO PUBLIC UTILITIES AND CARRIERS -- THE RENEWABLE ENERGY | |
GROWTH PROGRAM | |
| |
Introduced By: Representatives Chippendale, J. Brien, Paplauskas, Quattrocchi, | |
Date Introduced: April 09, 2025 | |
Referred To: House Corporations | |
It is enacted by the General Assembly as follows: | |
1 | SECTION 1. Chapter 39-26.6 of the General Laws entitled "The Renewable Energy |
2 | Growth Program" is hereby repealed in its entirety. |
3 | CHAPTER 39-26.6 |
4 | The Renewable Energy Growth Program |
5 | 39-26.6-1. Purpose. |
6 | The purpose of this chapter is to enable the state to meet its climate and resilience goals, |
7 | including those established in the act on climate. This includes the goals to facilitate and promote |
8 | installation of grid-connected generation of renewable energy; support and encourage development |
9 | of distributed renewable energy generation systems while protecting important core forest areas |
10 | essential to climate resilience and complying with Rhode Island’s climate change mandates; reduce |
11 | environmental impacts; reduce carbon emissions that contribute to climate change by encouraging |
12 | the siting of renewable energy projects in the load zone of the electric distribution company and in |
13 | preferred areas that have already been disturbed by industry or other uses; diversify the energy- |
14 | generation sources within the load zone of the electric distribution company; stimulate economic |
15 | development; and improve distribution-system resilience and reliability within the load zone of the |
16 | electric distribution company. |
17 | 39-26.6-2. Renewable energy growth program established. |
18 | To carry out these purposes, a tariff-based, renewable energy distributed-generation |
| |
1 | financing program, hereinafter referred to as the renewable energy growth program, is hereby |
2 | established with the intention of continuing the development of renewable energy distributed |
3 | generation in the load zone of the electric distribution company at reasonable cost. The program |
4 | shall be designed to finance the development, construction, and operation of renewable energy |
5 | distributed-generation projects over five (5) years through a performance-based incentive system |
6 | that is designed to achieve specified megawatt targets at reasonable cost through competitive |
7 | processes. The renewable energy growth program shall be implemented by the electric distribution |
8 | company, and guided by the distributed-generation board, in consultation with the office of energy |
9 | resources, subject to the review and supervision of the commission. |
10 | 39-26.6-3. Definitions. |
11 | When used in this chapter, the following terms shall have the following meanings: |
12 | (1) “Board” shall mean the distributed-generation board as established pursuant to the |
13 | provisions of § 39-26.2-10 under the title distributed generation standard contract board, but shall |
14 | also fulfill the responsibilities set forth in this chapter. |
15 | (2) “Ceiling price” means the bidding price cap(s) applicable to each annual enrollment for |
16 | a given distributed-generation class, that shall be approved for each renewable energy class |
17 | pursuant to the procedure established in this chapter. The ceiling price(s) are not required to, but |
18 | may be, approved for up to three years. The ceiling price for each technology should be a price that |
19 | would allow a private owner to invest in a given project at a reasonable rate of return, based on |
20 | recently reported and forecast information on the cost of capital and the cost of generation |
21 | equipment. The calculation of the reasonable rate of return for a project shall include, where |
22 | applicable, any state or federal incentives, including, but not limited to, tax incentives. Nothing |
23 | shall prohibit the distributed-generation board from proposing revised ceiling prices prior to a |
24 | program year to account for changes to available federal or state tax incentives, trade tariffs, or |
25 | other federal or state incentives that would affect the calculation of the rate of return on a project. |
26 | (3) “Commercial-scale solar project” means a solar distributed-generation project with the |
27 | nameplate capacity specified in § 39-26.6-7. |
28 | (4) “Commission” means the Rhode Island public utilities commission. |
29 | (5) “Community remote distributed-generation system” means a distributed-generation |
30 | facility greater than two hundred fifty kilowatt (250 KW) nameplate direct current that allocates |
31 | bill credits for each kilowatt hour (KWh) generated to a minimum of three (3), eligible recipient- |
32 | customer accounts, provided that no more than fifty percent (50%) of the credits produced by the |
33 | system are allocated to one eligible recipient-customer account, and provided further that at least |
34 | fifty percent (50%) of the credits produced by the system are allocated to eligible recipients in an |
| LC002551 - Page 2 of 24 |
1 | amount not to exceed that which is produced annually by twenty-five kilowatt (25 KW) AC |
2 | capacity. The community remote distributed-generation system may transfer credits to eligible |
3 | recipient-customer accounts in an amount that is equal to, or less than, the sum of the usage of the |
4 | eligible recipient-customer accounts measured by the three-year-average (3) annual consumption |
5 | of energy over the previous three (3) years. A projected, annual consumption of energy may be |
6 | used until the actual three-year-average (3) annual consumption of energy over the previous three |
7 | (3) years at the eligible recipient-customer accounts becomes available for use in determining |
8 | eligibility of the generating system. The community remote distributed-generation system may be |
9 | owned by the same entity that is the customer of record on the net-metered account or may be |
10 | owned by a third party. |
11 | (6) “Core forest” refers to unfragmented forest blocks of single or multiple parcels totaling |
12 | two hundred fifty (250) acres or greater unbroken by development and at least twenty-five (25) |
13 | yards from mapped roads, with eligibility questions to be resolved by the director of the department |
14 | of environmental management. Such determination shall constitute a contested case as defined in |
15 | § 42-35-1. Notwithstanding any other provisions of this chapter, no renewable-distributed- |
16 | generation project that is located or planned to be located in or on a core forest, shall be considered |
17 | an eligible renewable-distributed-generation project or otherwise be eligible to participate in this |
18 | program, unless it is on a preferred site. |
19 | (7) “Distributed-generation facility” means an electrical-generation facility located in the |
20 | electric distribution company’s load zone with a nameplate capacity no greater than five megawatts |
21 | (5 MW), except for solar projects as described in § 39-26.6-7 that may exceed five megawatts (5 |
22 | MW) but shall not be greater than fifteen megawatts (15 MW), unless located on preferred sites, in |
23 | which case they may be sized up to thirty-nine megawatts (39 MW), using eligible renewable |
24 | energy resources as defined by § 39-26-5, including biogas created as a result of anaerobic |
25 | digestion, but, specifically excluding all other listed eligible biomass fuels, and connected to an |
26 | electrical power system owned, controlled, or operated by the electric distribution company. For |
27 | facilities developed in core forests on preferred sites, no more than one hundred thousand square |
28 | feet (100,000 sq. ft.) of core forest shall be removed, except for work required for utility |
29 | interconnection or development of a brownfield, in which case no more core forest than necessary |
30 | for interconnection or brownfield development shall be removed. For purposes of this chapter, a |
31 | distributed-generation facility must be a new resource that: |
32 | (i) Has not begun operation; |
33 | (ii) Is not under construction, but excluding preparatory site work that is less than twenty- |
34 | five percent (25%) of the estimated total project cost; and |
| LC002551 - Page 3 of 24 |
1 | (iii) Except for small-scale solar projects, does not have in place investment or lending |
2 | agreements necessary to finance the construction of the facility prior to the submittal of an |
3 | application or bid for which the payment of performance-based incentives is sought under this |
4 | chapter except to the extent that such financing agreements are conditioned upon the project owner |
5 | being awarded performance-based incentives under the provisions of this chapter. For purposes of |
6 | this definition, preexisting hydro generation shall be exempt from the provisions of subsection |
7 | (7)(i) regarding operation, if the hydro-generation facility will need a material investment to restore |
8 | or maintain reliable and efficient operation and meet all regulatory, environmental, or operational |
9 | requirements. For purposes of this provision, “material investment” shall mean investment |
10 | necessary to allow the project to qualify as a new, renewable energy resource under § 39-26-2. To |
11 | be eligible for this exemption, the hydro-project developer at the time of submitting a bid in the |
12 | applicable procurement must provide reasonable evidence with its bid application showing the level |
13 | of investment needed, along with any other facts that support a finding that the investment is |
14 | material, the determination of which shall be a part of the bid review process set forth in § 39-26.6- |
15 | 16 for the award of bids. |
16 | (8) “Distributed-generation project” means a distinct installation of a distributed- |
17 | generation facility. An installation will be considered distinct if it does not violate the segmentation |
18 | prohibition set forth in § 39-26.6-9. |
19 | (9) “Electric distribution company” means a company defined in § 39-1-2(a)(12), |
20 | supplying standard-offer service, last-resort service, or any successor service to end-use customers, |
21 | but not including the Block Island Power Company or the Pascoag Utility District. |
22 | (10) “ISO-NE” means Independent System Operator-New England, the Regional |
23 | Transmission Organization for New England designated by the Federal Energy Regulatory |
24 | Commission. |
25 | (11) “Large distributed-generation project” means a distributed-generation project that has |
26 | a nameplate capacity that exceeds the size of a small distributed-generation project in a given year, |
27 | but is no greater than five megawatts (5 MW) nameplate capacity. |
28 | (12) “Large-scale solar project” means a solar distributed-generation project with the |
29 | nameplate capacity specified in § 39-26.6-7. |
30 | (13) “Medium-scale solar project” means a solar distributed-generation project with the |
31 | nameplate capacity specified in § 39-26.6-7. |
32 | (14) “Office” means the Rhode Island office of energy resources. |
33 | (15) “Preferred sites” means a location for a renewable energy system that has had prior |
34 | development, including, but not limited to: landfills, gravel pits and quarries, highway and major |
| LC002551 - Page 4 of 24 |
1 | road median strips, brownfields, superfund sites, parking lots or sites that are designated |
2 | appropriate for carports, and all rooftops including, but not limited to, residential, commercial, |
3 | industrial and municipal buildings. |
4 | (16) “Program year” means a year beginning April 1 and ending March 31, except for the |
5 | first program year, that may commence after April 1, 2015, subject to commission approval. |
6 | (17) “Renewable energy certificate” means a New England Generation Information System |
7 | renewable energy certificate as defined in § 39-26-2(14). |
8 | (18) “Renewable energy classes” means categories for different renewable energy |
9 | technologies using eligible renewable energy resources as defined by § 39-26-5, including biogas |
10 | created as a result of anaerobic digestion, but, specifically excluding all other listed eligible biomass |
11 | fuels specified in § 39-26-2(6). For each program year, in addition to the classes of solar distributed |
12 | generation specified in § 39-26.6-7, the board shall determine the renewable energy classes as are |
13 | reasonably feasible for use in meeting distributed-generation objectives from renewable energy |
14 | resources and are consistent with the goal of meeting the annual target for the program year. The |
15 | board may make recommendations to the commission to add, eliminate, or adjust renewable energy |
16 | classes for each program year, provided that the solar classifications set forth in § 39-26.6-7 shall |
17 | remain in effect for at least the first two (2) program years and no distributed-generation project |
18 | may exceed five megawatts (5 MW) of nameplate capacity except for solar projects as described |
19 | in § 39-26.6-7. |
20 | (19) “Shared solar facility” means a single small-scale or medium-scale solar facility that |
21 | must allocate bill credits to at least two (2), and no more than fifty (50), accounts in the same |
22 | customer class and on the same or adjacent parcels of land. Public entities may allocate such bill |
23 | credits to at least two (2), and up to fifty (50), accounts without regard to physical location so long |
24 | as the facility and accounts are within the same municipality. In no case will the annual allocated |
25 | credits in KWh exceed the prior three-year (3) annual average usage, less any reductions for verified |
26 | energy-efficiency measures installed at the customer premises, of the customer account to which |
27 | the bill credits are transferred. |
28 | (20) “Small distributed-generation project” means a distributed-generation renewable |
29 | energy project that has a nameplate capacity within the following: Wind: fifty kilowatts (50 KW) |
30 | to one and one-half megawatts (1.5 MW); small-scale solar projects and medium-scale solar |
31 | projects with the capacity limits as specified in § 39-26.6-7. For technologies other than solar and |
32 | wind, the board shall set the nameplate capacity-size limits, but such limits may not exceed one |
33 | megawatt (1 MW). |
34 | (21) “Small-scale solar project” means a solar distributed-generation project with the |
| LC002551 - Page 5 of 24 |
1 | nameplate capacity specified in § 39-26.6-7. |
2 | 39-26.6-4. Continuation of board. |
3 | (a) The distributed generation standard contract board shall remain fully constituted and |
4 | authorized as provided in chapter 26.2 of this title; provided, however, that the name shall be |
5 | changed to the “distributed-generation board.” Additional purposes of the board shall be to: |
6 | (1) Evaluate and make recommendations to the commission regarding ceiling prices and |
7 | annual targets, the make-up of renewable energy classifications eligible under the distributed- |
8 | generation growth program, the terms of the tariffs, and other duties as set forth in this chapter; |
9 | (2) Provide consistent, comprehensive, informed, and publicly accountable involvement |
10 | by representatives of all interested stakeholders affected by, involved with, or knowledgeable about |
11 | the development of distributed-generation projects that are eligible for performance-based |
12 | incentives under the distributed-generation growth program; and |
13 | (3) Monitor and evaluate the effectiveness of the distributed-generation growth program. |
14 | (b) The office, in consultation with the board, shall be authorized to hire, or to request the |
15 | electric distribution company to hire, the services of qualified consultants to perform ceiling price |
16 | studies subject to commission approval that shall be granted or denied within sixty (60) days of |
17 | receipt of such request from the office. The cost of the studies shall be recoverable through the rate- |
18 | reconciliation provisions of the electric distribution company set forth in § 39-26.6-25, subject to |
19 | commission approval. In addition, the office, in consultation with the board, may request the |
20 | commission to approve other costs incurred by the board, office, or the electric distribution |
21 | company to utilize consultants for annual programmatic services or to perform any other studies |
22 | and reports, subject to the review and approval of the commission, that shall be granted or denied |
23 | within one hundred twenty (120) days of receipt of the request from the office, and that shall be |
24 | recoverable through the same reconciliation provisions. |
25 | (c) Revenues generated through the rate reconciliation process to finance the expenses |
26 | incurred as outlined in subsection (b) shall be transferred to the office and deposited in a restricted- |
27 | receipt account within the general fund. The restricted-receipt account shall be exempt from the |
28 | indirect cost recovery assessment under § 35-4-27. |
29 | 39-26.6-5. Tariffs proposed and approved. |
30 | (a) Each year the electric distribution company shall file tariffs with the commission that |
31 | are designed to provide a multiyear stream of performance-based incentives to eligible renewable- |
32 | distributed-generation projects for a term of years, under terms and conditions set forth in the tariffs |
33 | and approved by the commission. The tariffs shall set forth the rights and obligations of the owner |
34 | of the distributed-generation project and the conditions upon which payment of performance-based |
| LC002551 - Page 6 of 24 |
1 | incentives by the electric distribution company will be paid. The tariffs shall include the non-price |
2 | conditions set forth in §§ 39-26.2-7(2)(i) — (vii) for small distributed-generation projects (other |
3 | than small- and medium-scale solar) and large distributed-generation projects; provided, however, |
4 | that the time periods for the projects to reach ninety percent (90%) of output shall be extended to |
5 | twenty-four (24) months (other than eligible anaerobic-digestion projects, which shall be thirty-six |
6 | (36) months, and eligible small-scale hydro, and large-scale solar projects which shall be forty- |
7 | eight (48) months). The non-price conditions in the tariffs for small- and medium-scale solar shall |
8 | take into account the different circumstances for distributed-generation projects of the smaller sizes. |
9 | (b) In addition to the tariff(s), the filing shall include the rules governing the solicitation |
10 | and enrollment process. The solicitation rules will be designed to ensure the orderly functioning of |
11 | the distributed-generation growth program and shall be consistent with the legislative purposes of |
12 | this chapter. |
13 | (c) In proposing the tariff(s) and solicitation rules applicable to each year, the tariff(s) and |
14 | rules shall be developed by the electric distribution company and will be reviewed by the office |
15 | and the board before being sent to the commission for its approval. The proposed tariffs shall |
16 | include the ceiling prices and term lengths for each tariff that are recommended by the board. The |
17 | term lengths shall be from fifteen (15) to twenty (20) years; provided, however, that the board may |
18 | recommend shorter terms for small-scale solar projects. Whatever term lengths between fifteen |
19 | (15) and twenty (20) years are chosen for any given tariff, the evaluation of the bids for that tariff |
20 | shall be done on a consistent basis such that the same term lengths for competing bids are used to |
21 | determine the winning bids. |
22 | (d) In setting the ceiling prices, the board may specifically consider: |
23 | (1) Transactions for newly developed renewable energy resources, by technology and size, |
24 | in the ISO-NE control area and the northeast corridor; |
25 | (2) Pricing from bids received during the previous program year; |
26 | (3) Environmental benefits, including, but not limited to, reducing carbon emissions; |
27 | (4) For community remote distributed-generation systems, administrative costs and |
28 | financial benefits for participating customers; |
29 | (5) System benefits; |
30 | (6) Cost-effectiveness; |
31 | (7) Location of projects, including climate resilience and conservation benefits; and |
32 | (8) Labor standards pursuant to chapter 26.9 of this title. |
33 | (e) At least forty-five (45) days before filing the tariff(s) and solicitation rules, the electric |
34 | distribution company shall provide the tariff(s) and rules in draft form to the board for review. The |
| LC002551 - Page 7 of 24 |
1 | commission shall have the authority to determine the final terms and conditions in the tariff and |
2 | rules. Once approved, the commission shall retain exclusive jurisdiction over the performance- |
3 | based incentive payments, terms, conditions, rights, enforcement, and implementation of the tariffs |
4 | and rules, subject to appeals pursuant to chapter 5 of this title. |
5 | 39-26.6-6. Permanence of tariff terms once set. |
6 | It is the intention of the general assembly in enacting this chapter that the developers, |
7 | owners, investors, customers, and lenders of the distributed-generation projects receiving |
8 | performance-based incentives under the tariffs be able to rely on the tariffs for the entire term of |
9 | the applicable tariff for purposes of obtaining financing. Consistent with that intention and |
10 | expectation, the terms under the tariffs for a given program year, once approved by the commission, |
11 | shall not be altered in any way that would undermine such reliance on those tariffs during the |
12 | applicable terms of the tariffs; and in no circumstance will the performance-based incentive rate |
13 | paid to a renewable energy project developer or owner be reduced during the term of the tariff once |
14 | a renewable energy project has qualified to receive a tariff under the terms of this chapter. |
15 | 39-26.6-7. Solar project size categories. |
16 | (a) Tariff(s) shall be proposed for each of the following solar distributed-generation |
17 | classes: |
18 | (1) Small-scale solar projects; |
19 | (2) Medium-scale solar projects; |
20 | (3) Commercial-scale solar projects; and |
21 | (4) Large-scale solar projects. |
22 | (b) Such classes of solar distributed-generation projects shall be established based on |
23 | nameplate megawatt size as follows: |
24 | (1) Large-scale solar projects shall be comprised of four (4) classes as follows: |
25 | (i) One megawatt (1 MW) but less than five megawatts (5 MW), nameplate capacity; |
26 | (ii) Five megawatts (5 MW), but less than ten megawatts (10 MW), nameplate capacity; |
27 | (iii) Ten megawatts (10 MW), but less than fifteen megawatts (15 MW), nameplate |
28 | capacity; and |
29 | (iv) Fifteen megawatts (15 MW), but less than thirty-nine megawatts (39 MW), nameplate |
30 | capacity for projects located on preferred sites; |
31 | (2) Commercial scale shall be comprised of solar projects greater than two hundred fifty |
32 | kilowatts (250 KW), but less than one megawatt (1 MW) nameplate capacity; |
33 | (3) Medium scale shall be comprised of solar projects greater than twenty-five kilowatts |
34 | (25 KW), up to and including, two hundred fifty kilowatts (250 KW) nameplate capacity; and |
| LC002551 - Page 8 of 24 |
1 | (4) Small scale shall be comprised of solar projects up to and including twenty-five |
2 | kilowatts (25 KW) nameplate capacity. |
3 | (c) Other classifications of solar projects may also be proposed by the board, subject to the |
4 | approval of the commission. After the second program year, the board may make recommendations |
5 | to the commission to adjust the size categories of the solar classes, provided that the medium-scale |
6 | solar projects may not exceed two hundred fifty kilowatts (250 KW); and/or allocated capacity to |
7 | community distributed-generation facilities, allowing them to compete or enroll under a distinct |
8 | ceiling price. |
9 | 39-26.6-8. Renewable technologies other than solar. |
10 | Tariffs also shall be proposed for on-shore wind and any other distributed-generation |
11 | technologies permissible under this chapter that the board, in its discretion, recommends; provided, |
12 | however, that no project shall exceed five megawatts (5 MW) nameplate capacity. The electric |
13 | distribution company shall file tariffs for each technology and size categories recommended by the |
14 | board pursuant to the procedures set forth in this chapter. |
15 | 39-26.6-9. Project segmentation prohibition. |
16 | In no case may a project developer be allowed to segment a distributed-generation project |
17 | on the same parcel or contiguous parcels into smaller-sized projects in order to fall under a smaller- |
18 | size project classification. Notwithstanding this prohibition, a project developer may designate a |
19 | generation unit on the same parcel or contiguous parcel for net metering or other means of |
20 | participating in electricity markets, provided that the unit, or portion of the unit, designated for net |
21 | metering or other market participation is not receiving performance-based incentives under this |
22 | chapter; is capable of being segregated electrically; is configured with the electrical segregation; |
23 | and is separately metered. Further, a project shall not be considered to have been segmented if: |
24 | (1) There is a lapse of at least twenty-four (24) months between: (i) The commencement |
25 | of construction of new distributed-generation units on a parcel that is the same as, or is contiguous |
26 | with, a parcel upon which a distributed-generation project has already been constructed; and (ii) |
27 | The operation date of the preexisting project; or |
28 | (2) The new project is a different renewable technology. |
29 | 39-26.6-10. Timing and schedule of tariff filings. |
30 | (a) The electric distribution company shall file with the commission the first set of tariffs |
31 | and solicitation rules pursuant to this chapter no later than November 15, 2014. Thereafter, the |
32 | electric distribution company shall make tariff and solicitation rules filings with the commission |
33 | no later than November 15 prior to the beginning of the applicable program year when necessary, |
34 | which tariffs and rules shall be applicable for the next program year(s). |
| LC002551 - Page 9 of 24 |
1 | (b) Upon receiving the filing from the electric distribution company, the commission shall |
2 | open a docket to consider the filing. The commission shall issue an order approving the proposed |
3 | tariffs and solicitation rules; provided, however, that the commission may make any modifications |
4 | that it deems appropriate consistent with the legislative purposes of this chapter as set forth herein. |
5 | (c) The commission shall approve tariff(s) and solicitation rules prior to the |
6 | commencement of the applicable year(s). |
7 | (d) During the course of any program year, the electric distribution company may, at any |
8 | time, in consultation with the office and the board, propose tariff or solicitation rules modifications. |
9 | The commission shall consider the proposed modifications through an already open or new docket, |
10 | and shall issue its order within one hundred five (105) days of the filing of the proposed |
11 | modification. If approved, the proposed modification shall take effect for the next enrollment event |
12 | following the issuance of the commission’s order. |
13 | 39-26.6-11. Power purchase agreements not required. |
14 | The distributed-generation growth program shall be implemented and administered |
15 | exclusively through the tariff structure and procedures set forth in this chapter, and the electric |
16 | distribution company shall not be required to execute power purchase agreements for the |
17 | procurement of the renewable energy distributed-generation capacity requirements set forth in this |
18 | chapter. |
19 | 39-26.6-12. Annual bidding and enrollments. |
20 | (a) The electric distribution company, in consultation with the board and office, shall |
21 | conduct at least three (3) tariff enrollments for each distributed-generation class each program year. |
22 | (b) During each program year, the tariff enrollments shall have both an annual targeted |
23 | amount of nameplate megawatts (“annual MW target”) and a nameplate megawatt target for each |
24 | separate enrollment event (“enrollment MW target”). The enrollment MW target shall comprise the |
25 | specific portion of the annual MW target sought to be obtained in that enrollment. The annual MW |
26 | target(s) and enrollment MW targets shall be recommended by the board no less frequently than |
27 | every three (3) years, subject to commission approval. The board shall also recommend a megawatt |
28 | target for each class (“class MW target”) that comprises a specified portion of the enrollment MW |
29 | target, subject to commission approval. If the electric distribution company, the office, and the |
30 | board mutually agree, they may reallocate megawatts during an enrollment from one class to |
31 | another without commission approval if there is an over-subscription in one class and an under- |
32 | subscription in another, provided that the annual MW target is not being exceeded, except as |
33 | provided in § 39-26.6-17. No reallocation of megawatts from a competitive pricing class to a non- |
34 | competitive pricing class shall be made until after the completion of the three (3) enrollment periods |
| LC002551 - Page 10 of 24 |
1 | in the program year and in no case may the annual MW target be exceeded as a result of a |
2 | reallocation of megawatts. |
3 | (c) The annual MW targets shall be established from the year 2023 through the year 2033. |
4 | The annual target for each program year shall be up to three hundred megawatts (300 MW); |
5 | provided that, thirty megawatts (30 MW) shall be reserved for projects less than one megawatt (1 |
6 | MW). The board may petition the commission for approval of multi-year annual targets and |
7 | associated-ceiling prices. |
8 | (d) – (j) [Deleted by P.L. 2023, ch. 300, § 2 and P.L. 2023, ch. 301, § 2.] |
9 | 39-26.6-13. Cost reconciliation. |
10 | To the extent the electric distribution company incurs incremental costs to meet the |
11 | program objectives or make billing system improvements that are required to facilitate payments |
12 | of performance-based incentives and administering net metering, the electric distribution company |
13 | may elect to recover those incremental costs through the annual charge set forth in § 39-26.6-25, |
14 | subject to commission review and approval that assures such costs were properly and prudently |
15 | incurred. |
16 | 39-26.6-14. Existing powers of agencies and advocacy rights of parties unchanged. |
17 | Nothing in this chapter shall be construed to derogate from the statutory authority of the |
18 | commission or the division of public utilities and carriers, including, but not limited to, the authority |
19 | to protect ratepayers from unreasonable rates. Nothing in this chapter shall be construed to preclude |
20 | any party from advocating a position in commission proceedings that differs from the |
21 | recommendations made by the board to the commission or in any filing with the commission |
22 | relating to this chapter, including, without limitation: (1) Individual or organizational members of |
23 | the board; (2) Participants in board deliberations; (3) The office; and (4) The electric distribution |
24 | company, unless the party has consented by vote to the execution or executed a settlement |
25 | agreement agreeing to the terms, policy proposals, or any other matter proposed to the commission. |
26 | 39-26.6-15. Bidding and incentive award processes for solar DG projects. |
27 | (a) Large-scale and commercial-scale solar projects and distributed-generation projects for |
28 | other eligible technologies shall bid a price-per-kilowatt-hour for the entire output of the facility |
29 | (net of any station service) that shall not exceed the applicable ceiling price. Small-scale and |
30 | medium-scale solar projects will submit an enrollment application to receive a standard |
31 | performance-based incentive for the period of years in the applicable tariff, that shall be a price- |
32 | per-kilowatt-hour for the entire output of the facility. Except for megawatts that may be allocated |
33 | to the energy-efficiency program pursuant to § 39-26.6-19, small- and medium-scale projects shall |
34 | be selected on a first-come, first-served basis, or by means of a commission-approved lottery |
| LC002551 - Page 11 of 24 |
1 | system, or such other method as may be recommended by the board and approved by the |
2 | commission. |
3 | (b) Except for the first program year, the board shall determine, subject to commission |
4 | approval, the standard performance-based incentive for small- and medium-sized solar projects |
5 | from the average bid price from the last two (2) procurement enrollments conducted in the |
6 | commercial-scale and/or large-scale solar projects class. The standard performance incentive may |
7 | be set at a higher rate than payments for commercial-scale and large-scale solar projects in order to |
8 | take into account the potentially higher per-unit cost of smaller projects. The standard performance |
9 | incentive also shall be adjusted upward or downward, as needed, in order to take into account the |
10 | term length over which the incentive shall be paid for the small- and medium-scale solar projects |
11 | if such terms are different than the terms applicable to the classes from which the standard |
12 | performance incentive was derived. |
13 | (c) For each program year, the board shall recommend to the commission a standard |
14 | performance incentive for each of the small-scale and medium-scale solar project classifications, |
15 | which performance incentives may span up to three program years. Upon receiving the |
16 | recommendations from the board, the commission shall open a docket to consider the |
17 | recommendations or address the recommendations in its approval process for the applicable |
18 | program year(s) in a consolidated docket as provided in § 39-26.6-10. The commission shall issue |
19 | its order approving the recommendations no later than concurrently with approval of the entire |
20 | program and tariffs applicable to the program year; provided, however, that the commission may |
21 | make modifications or changes to the board’s recommendations consistent with the legislative |
22 | purposes of this chapter. |
23 | (d) If after the first program year, the applications for the medium-scale solar projects are |
24 | significantly over-subscribed, then the board and the electric distribution company, in consultation |
25 | with the office, may propose to the commission a bidding process for medium-scale projects or a |
26 | subset of the medium-scale projects under which project selections would be made based on the |
27 | lowest bids, rather than first-come, first-served or such other method previously approved by the |
28 | commission. The commission shall approve the proposal from the board and electric company |
29 | within ninety (90) days; provided, however, that the commission may make changes to the proposal |
30 | consistent with the legislative purposes of this chapter. |
31 | (e) The commission shall approve the bidding process for medium-scale solar projects |
32 | recommended by the board only if the commission finds that such bidding process is in a |
33 | sufficiently simple form that is not administratively burdensome to bidders, and will not have the |
34 | effect of discouraging participation in the distributed-generation growth program by developers of |
| LC002551 - Page 12 of 24 |
1 | medium-scale solar projects that may be unrepresented by counsel. |
2 | 39-26.6-16. Enrollment program. |
3 | (a) Each enrollment shall be open for a two-week (2) period during which the electric |
4 | distribution company is required to receive standard short-form applications. The standard short- |
5 | form application shall require the applicant to provide the following information: the project |
6 | owner’s identity; the location of the proposed project; the nameplate capacity of the proposed |
7 | project; and renewable energy class of the proposed project. The standard short-form application |
8 | shall allow project owners to provide additional information relative to the permitting, financial |
9 | feasibility, ability to build, and timing for deployment of the proposed projects. The applicant must |
10 | submit an affidavit with the standard short-form application confirming that the project is not in |
11 | violation of the rules that prohibit project segmentation, as set forth in § 39-26.6-9. |
12 | (b) For large distributed-generation projects only, the standard short-form application shall |
13 | also require the applicant to bid a bundled price that applies to the energy, renewable energy |
14 | certificates, and all other environmental attributes and market products that are available, or may |
15 | become available, from the distributed-generation facility on a per-kilowatt-hour basis measured |
16 | from the output of the project. At the election of the electric distribution company, and subject to |
17 | the approval of the commission, the bid may be required to include the sale of capacity. |
18 | (c) For (i) Small distributed-generation projects other than small-scale and medium-scale |
19 | solar projects; and (ii) Large distributed-generation projects, the electric distribution company shall |
20 | select projects based on the lowest proposed prices received that do not exceed the ceiling price |
21 | from the distributed-generation projects that meet the requirements of all applicable tariffs and |
22 | regulations, and meet the criteria of the renewable energy class in effect, until the class target is |
23 | met. Performance-based incentives shall be awarded to the winning bidders based on their bids |
24 | submitted. |
25 | (d) For small-scale and medium-scale solar projects, awards shall be made in the manner |
26 | set forth in §§ 39-26.6-15 and 39-26.6-19. |
27 | (e) If there are more projects bidding at the same price than the capacity that is specified |
28 | for a class target, the electric distribution company shall, in consultation with the board and the |
29 | office, select first those projects that appear to be the furthest along in development and that are |
30 | most likely to be deployed. Those projects that are likely to be deployed at the earliest time shall |
31 | be selected first. To the extent the electric distribution company is unable to make a clear distinction |
32 | on this basis, the electric distribution company shall report its findings to the board and not award |
33 | bids for those projects that are tied on pricing. In that case, the board may take such action as it |
34 | deems appropriate for the selection of projects, including seeking more information from the |
| LC002551 - Page 13 of 24 |
1 | projects. |
2 | (f) Should the electric distribution company determine that it has made sufficient awards |
3 | to achieve a program-year class target, it shall immediately report this fact to the board, the office, |
4 | and the commission, and may cease making awards for that renewable energy class for the |
5 | remainder of the program year. In any event, the electric distribution company may exceed the |
6 | renewable energy class target if the last award may cause the total purchased to exceed the target. |
7 | (g) The board, the office, and the electric distribution company shall enter into a |
8 | memorandum of understanding regarding the sharing of the information and data related to the |
9 | renewable energy growth program, including, without limitation, information on bids received, |
10 | details regarding project ownership, and pricing. At the request of the board, the office, or the |
11 | electric distribution company, the commission shall have the authority to protect from public |
12 | disclosure individual bid information for any projects that have not been awarded performance- |
13 | based incentives. |
14 | (h) The electric distribution company is authorized to award bids up to the applicable |
15 | ceiling price. As long as the terms of the tariff are met, and the pricing is no higher than the |
16 | applicable ceiling price, such awards shall be deemed prudent and approved by the commission for |
17 | purposes of recovering the costs in rates. |
18 | (i) With respect to any procurement that includes bids from pre-existing, hydroelectric |
19 | generation, the electric distribution company, in consultation with the office, shall have the |
20 | authority to accept the applicant’s representation that its investment is material, within the meaning |
21 | of § 39-26.6-3(7). However, if the electric distribution company or the office questions whether the |
22 | material investment standard has been met or the application is otherwise rejected, the application |
23 | shall be submitted to the board for review and the board shall draw its own conclusion and make a |
24 | recommendation to the commission at the time the commission is approving awards from the |
25 | procurement to which the application pertains. The commission shall have the final authority to |
26 | make the determination as to whether the material investment standard has been met. Nothing in |
27 | this subsection shall preclude a project developer from seeking a preliminary confirmation of |
28 | eligibility for the material-investment exemption from the electric distribution company, the office, |
29 | and the board prior to the submittal of a bid. In such case, if there is any disagreement, the final |
30 | determination shall be submitted to the commission. |
31 | 39-26.6-17. Excess enrollment not required. |
32 | The electric distribution company shall not be required to award bids in excess of the |
33 | annual target for the applicable program year and shall not be required to procure projects in excess |
34 | of any limit set by the board and approved by the commission for a given enrollment. However, |
| LC002551 - Page 14 of 24 |
1 | the electric distribution company, in consultation with the board and the office, may voluntarily |
2 | exceed an enrollment period limit as long as it does not exceed an annual target for the applicable |
3 | program year. At its election, the electric distribution company may exceed an annual target for the |
4 | applicable program year after review by the board and approval by the commission. |
5 | 39-26.6-18. Utility right to separately meter. |
6 | Owners of medium-scale, commercial-scale, and large-scale solar projects and other |
7 | distributed-generation technologies shall be required to provide, at their cost, a revenue-quality |
8 | meter to standards approved by the division of public utilities and carriers and provide access to |
9 | the information from the meter to the electric distribution company to measure the output of the |
10 | generation. The electric distribution company shall have the discretion to install the second meter |
11 | in a parallel configuration to the retail meter or behind the meter, provided that a parallel installation |
12 | shall have no effect on the right of the customer to net meter using the net of the two meters. The |
13 | electric distribution company also shall have the right to install its own revenue-quality meter for |
14 | small-scale solar projects if not being supplied by the owner. The electric distribution company |
15 | shall recover the installation and capital cost of the separate meters it installs for small-scale solar |
16 | projects in the annual reconciliation of solar costs under § 39-26.6-25. |
17 | 39-26.6-19. Coordination with energy-efficiency programs. |
18 | (a) In consultation with the office, the electric distribution company may make a request to |
19 | the commission that up to half of the megawatts for the small- and medium-scale solar project |
20 | enrollments be allocated by the commission for selection through a process coordinated with the |
21 | energy-efficiency program in order that specified solar incentives may be tied with energy- |
22 | efficiency program incentives in order to allow the electric distribution company to implement a |
23 | coordinated, energy efficiency and solar program offering. In this case, the electric distribution |
24 | company will propose criteria for eligibility for performance-based incentives for solar that require |
25 | certain energy-efficiency standards be met at the customer location in order to be eligible for |
26 | performance-based incentives for a small-scale and/or medium-scale solar installation. |
27 | (b) The electric distribution company must also include program parameters that do not |
28 | disrupt competition among small-scale and/or medium-scale solar developers, including, without |
29 | limitation, safeguards against any one, or subset of, developers in this market being given exclusive |
30 | rights or other market advantages over competitors. In approving the proposal, the commission |
31 | must find that there is no such small- and medium-solar-market disruption. |
32 | (c) The commission shall approve the request of the distribution company within ninety |
33 | (90) days, making such modifications as it deems reasonable, provided the modifications are |
34 | consistent with the legislative purposes of this chapter and the state’s energy-efficiency goals. |
| LC002551 - Page 15 of 24 |
1 | (d) The allocation of megawatts is for implementation purposes only and shall not authorize |
2 | funds to be shifted from the distributed-generation growth program to energy-efficiency programs, |
3 | nor will implementation of the electric distribution company’s request cause a reduction of the |
4 | annual or cumulative capacity goals established for the distributed-generation growth program. To |
5 | the extent that the megawatts allocated to the energy-efficiency program pursuant to this section |
6 | are not committed during a program year, such uncommitted megawatts shall be allocated back to |
7 | the distributed-generation growth program in the following year or such year the board |
8 | recommends to the commission. Funding for the energy-efficiency measures that are tied to the |
9 | solar installations must be obtained separately from the energy-efficiency program budget funded |
10 | through applicable energy-efficiency charges. |
11 | (e) Should the small-scale and medium-scale project classes in the renewable energy |
12 | growth program be oversubscribed in two (2) consecutive enrollments and there are megawatts that |
13 | have not been committed through the process coordinated with the energy-efficiency program after |
14 | the second enrollment, the board, after consultation with the office and the electric distribution |
15 | company, shall have the authority to move all, or a portion of, the uncommitted megawatts out of |
16 | the coordinated program back to the renewable energy growth program to meet the demand of the |
17 | oversubscription, subject to commission approval. If, in such case, the board does not exercise the |
18 | authority, any party may file a petition to the commission requesting action to be taken. |
19 | 39-26.6-20. Issuance of certificates and right to incentive payments. |
20 | (a) For small-scale and medium-scale solar projects, the electric distribution company shall |
21 | provide certificates of eligibility to the selected projects without commission confirmation of |
22 | approval (“distribution company awarded certificates”), subject to the review and consent of the |
23 | office. The electric distribution company shall file with the commission a list of all these |
24 | distribution-company-awarded certificates. |
25 | (b) For commercial-scale and large-scale solar, and all other distributed-generation |
26 | projects, the electric distribution company shall file with the commission a list of the distributed- |
27 | generation projects selected together with the corresponding pricing information. Within sixty (60) |
28 | days of receipt of the list, the commission shall issue an order awarding certificates of eligibility to |
29 | the distributed-generation projects (“PUC awarded certificates”). |
30 | (c) Upon receipt of a PUC-awarded certificate or a distribution-company certificate, a |
31 | distributed-generation project shall be entitled to receive, and the electric distribution company |
32 | shall pay and/or credit (as applicable), the performance-based incentives for the specified term, and |
33 | under the terms and conditions of the applicable tariff in the manner set forth below. |
34 | (d) The performance-based incentive shall be the price-per-kilowatt-hour that was bid and |
| LC002551 - Page 16 of 24 |
1 | awarded, or established as a standard incentive, as applicable. The performance-based incentive |
2 | shall be applied as a price-per-kilowatt-hour for all kilowatt-hours actually produced from the |
3 | distributed generation (net of station service, if any) for the term of years specified in the applicable |
4 | tariff, less the value of any kilowatt-hour charges that were offset by any net metering (if applicable) |
5 | for the host customer associated with the distributed generation for the billing month; provided, |
6 | however, if the value of kilowatt-hour charges that otherwise would be offset by net metering in a |
7 | given month exceeds the total value of the performance-based incentive for the month, the customer |
8 | shall not be subject to any additional charge, nor receive any additional net-metering credit, for the |
9 | difference between the performance-based incentive value and net-metering value for the month. |
10 | (e) Except as provided herein for residential small-scale solar projects, in every case where |
11 | a distributed-generation project can be configured for net metering, it shall be the election of the |
12 | owner of the generation to choose one of two (2) separate methods through which the owner will |
13 | be compensated for the performance-based incentive: |
14 | (1) The owner is compensated solely through direct payments under the performance-based |
15 | incentive provisions of this chapter for the life of the tariff term with no net metering implemented; |
16 | or |
17 | (2) The owner is compensated through a combination of direct payments and the bill credit |
18 | value of net metering for the life of the term of the tariff under the provisions of this chapter. |
19 | (3) In the case of residential small-scale solar projects, only option (2) shall be available. |
20 | (4) In either option, the total value of the performance-based incentive per-kilowatt-hour |
21 | is the same. An owner shall have a one-time right to switch the compensation methods after the |
22 | generation commences operation, provided that at least sixty (60) days’ notice is given to the |
23 | electric distribution company. Thereafter, any further compensation method switches shall be at |
24 | the sole discretion of the electric distribution company if requested again by the owner. |
25 | (f) Every owner who elects the compensation method shall: |
26 | (1) Receive compensation solely in the form of a check from the electric distribution |
27 | company, or other payment method that is mutually agreed between the electric distribution |
28 | company and the owner; and |
29 | (2) Shall receive compensation in the form of offsets against its electricity bill from the |
30 | electric distribution company from net metering and the balance in the form of a check from the |
31 | electric distribution company, or other payment method that is mutually agreed upon between the |
32 | electric distribution company and the owner; provided, however, that no owner of a distributed- |
33 | generation project may be compensated twice for the same kilowatt hour of electricity, and that |
34 | every self-generator shall receive the full pecuniary benefit of its election to participate in the |
| LC002551 - Page 17 of 24 |
1 | performance-based incentive program. |
2 | (g) Every owner of a distributed-generation project that can be configured for net metering |
3 | that elects the first option for compensation under the provisions of subsection (e) shall become |
4 | eligible to net meter its output in conformity with the provisions of existing law upon the |
5 | completion of the full term of the applicable tariff. Nothing in this section shall preclude a customer |
6 | from electing not to participate in the performance-based program and electing simply to net meter |
7 | under the provisions of existing law; provided, however, once an election is made to participate, |
8 | the customer will remain subject to the performance-based tariff conditions and may not terminate |
9 | the arrangement without the consent of the electric distribution company. |
10 | (h) As provided in § 39-26.6-9, any project developer may designate a generation unit on |
11 | the same parcel or contiguous parcel for net metering, provided that such unit or portion of such |
12 | unit designated for net metering is not receiving performance-based incentives under this chapter, |
13 | is capable of being segregated electrically, is configured with such electrical segregation, and is |
14 | separately metered. |
15 | (i) All distributed-generation projects accepting certificates shall be obligated to abide by |
16 | all the terms and conditions of the approved, applicable tariff. |
17 | 39-26.6-21. Ownership of output, other attributes, and renewable energy certificates. |
18 | (a) Except as provided herein for residential small-scale solar projects, distributed- |
19 | generation projects participating in the renewable energy growth program shall transfer to the |
20 | electric distribution company the rights and title to: |
21 | (1) Those renewable energy certificates generated by the project during the term of the |
22 | applicable, performance-based incentive tariff; |
23 | (2) All energy produced by the generation that is not otherwise consumed on site under a |
24 | net-metering arrangement; and |
25 | (3) Rights to any other environmental attributes or market products that are created or |
26 | produced by the project; provided, however, that it shall be the election of the electric distribution |
27 | company whether it chooses to acquire the capacity of the distributed-generation projects under the |
28 | tariffs set forth in this chapter and no ceiling prices recommended by the board and approved by |
29 | the commission will be adjusted downward in light of the electric distribution company’s election. |
30 | The electric distribution company shall: (1) Sell any products acquired and credit them to the |
31 | reconciliation account specified in § 39-26.6-25; and/or (2) Use the products to serve customers |
32 | and establish a price to be credited by customers using the products based on recent and near-term |
33 | projections of market prices. When a generator reverts to net metering after the end of the tariff |
34 | term under the renewable energy growth program, the net-metering generator shall retain title to |
| LC002551 - Page 18 of 24 |
1 | the renewable energy certificates generated by the project. In the case of residential small-scale |
2 | projects, title to all energy and capacity produced from the solar generation shall remain with the |
3 | residential customer; shall not be transferred to the electric distribution company; and shall be |
4 | deemed consumed by the residential customer on-site during the applicable, distribution-service |
5 | billing period with no sale or purchase between the residential customer and the electric distribution |
6 | company. |
7 | (b) For the accounting purposes of the electric distribution company in treating the |
8 | performance-based incentives, the cost of the energy that is procured shall be the real-time market |
9 | price of energy and the balance of the performance-based incentive shall be attributable to the |
10 | purchase of environmental and any other attributes acquired. This accounting shall have no effect |
11 | on the total, bundled performance-based incentive to which the distributed-generation project is |
12 | entitled under the provisions of this chapter. |
13 | 39-26.6-22. Zonal and other incentive payments. |
14 | In order to provide the electric distribution company and the board with the flexibility to |
15 | encourage distributed-generation projects to be located in designated geographical areas within its |
16 | load zone where there is an identifiable system benefit, reliability benefit, or cost savings to the |
17 | distribution system in that geographical area, or conservation benefit, or climate resilience benefit |
18 | in that geographical area, the electric distribution company, the board, or the office, shall propose |
19 | to include an incentive-payment adder to the bid price of any winning bidder that proposes a |
20 | distributed-generation project in the preferred sites that require remediation. The company, board, |
21 | or office can also propose disincentive subtractors for projects outside of preferred sites. The |
22 | electric distribution company also may propose other incentive payments to achieve other technical |
23 | or public policy objectives that provide identifiable benefits to customers. Any incentive-payment |
24 | adders must be approved by the commission, and shall not be counted as part of the bid price when |
25 | the bids are selected at an enrollment event. |
26 | 39-26.6-23. Intersection of distributed generation and net metering. |
27 | (a) Net-metering credits for excess generation shall not be credited during the term of the |
28 | tariff when the distributed-generation project is receiving performance-based incentive payments |
29 | under the tariff. After the end of the term of the performance-based incentive tariff applicable to a |
30 | distributed-generation project, net-metering credits for excess generation in any given month shall |
31 | be credited to the net-metered account at the applicable rate allowed under the law. |
32 | (b) All distributed-generation projects that had begun development prior to the date the |
33 | commission approves the first set of ceiling price recommendations from the board and that are in |
34 | operation by no later than July 1, 2016, shall be eligible to continue operation under the net- |
| LC002551 - Page 19 of 24 |
1 | metering rules that would have been applicable to that self-generation project absent the change in |
2 | law set forth in this section, provided that the project does not otherwise participate in the |
3 | performance-based incentive program set forth in this chapter. |
4 | 39-26.6-24. Rate design review by the commission. |
5 | (a) On or after July 1, 2015, the commission shall open a docket to consider rate design |
6 | and distribution cost allocation among rate classes in light of net metering and the changing |
7 | distribution system that is expected to include more distributed-energy resources, including, but |
8 | not limited to, distributed generation. The commission will determine the appropriate cost |
9 | responsibility and contributions to the operation, maintenance, and investment in the distribution |
10 | system that is relied upon by all customers, including, without limitation, non-net-metered and net- |
11 | metered customers. In that docket, the commission shall require the electric distribution company |
12 | to file a revenue-neutral allocated-cost-of-service study for all rate classes and a proposal for new |
13 | rates for all customers in each rate class. The electric distribution company shall use the |
14 | distribution-revenue requirement upon which the then-current distribution rates were set. The |
15 | electric distribution company may use the allocated cost of service that was filed with the |
16 | compliance filing from the rate case when the then-current distribution rates were set. The |
17 | commission may also address the rate design for the equitable recovery of costs associated with |
18 | energy efficiency and any renewable energy programs that are recovered in rates. |
19 | (b) In establishing any new rates the commission may deem appropriate, the commission |
20 | shall take into account and balance the following factors: |
21 | (1) The benefits of distributed-energy resources; |
22 | (2) The distribution services being provided to net-metered customers when the distributed |
23 | generation is not producing electricity; |
24 | (3) Simplicity, understandability, and transparency of rates to all customers, including non- |
25 | net-metered and net-metered customers; |
26 | (4) Equitable ratemaking principles regarding the allocation of the costs of the distribution |
27 | system; |
28 | (5) Cost causation principles; |
29 | (6) The general assembly’s legislative purposes in creating the distributed-generation |
30 | growth program; and |
31 | (7) Any other factors the commission deems relevant and appropriate in establishing a fair |
32 | rate structure. The rates shall be designed for each proposed rate class in accordance with industry- |
33 | standard, cost-allocation principles. The commission may consider any reasonable rate design |
34 | options, including without limitation, fixed charges, minimum-monthly charges, demand charges, |
| LC002551 - Page 20 of 24 |
1 | volumetric charges, or any combination thereof, with the purpose of assuring recovery of costs |
2 | fairly across all rate classes. |
3 | (c) The commission shall issue an order in the docket by no later than March 1, 2016. Any |
4 | new rates shall take effect for usage on and after April 1, 2016; provided, however, that the electric |
5 | distribution company may seek an extension if necessary to make the billing system changes |
6 | necessary to implement a new rate structure. After new, revenue-neutral rates are set in the docket |
7 | specified above, the commission may approve changes to the rate design in any future distribution- |
8 | base-rate cases when a fully allocated embedded cost-of-service study is being reviewed in the rate |
9 | case, subject to the principles set forth in subsection (b) of this section. |
10 | 39-26.6-25. Forecasted rate and reconciliation. |
11 | (a) On or before November 15 of each year, the electric distribution company shall file a |
12 | forecast of the total amount of payments that is likely to be paid out to distributed-generation |
13 | projects in the coming program year within the electric distribution company’s load zone, along |
14 | with any costs permitted for recovery pursuant to §§ 39-26.6-4, 39-26.6-13, and 39-26.6-18. The |
15 | total of all forecasted payments and costs shall be aggregated, net of forecasted revenues from the |
16 | sale of the energy, renewable energy certificates, and any other market products from the |
17 | distributed-generation projects participating in the performance-based incentive program. The |
18 | forecasted net-aggregate amount shall be used to design a fixed monthly charge per customer to |
19 | recover the net forecast in rates charged to all distribution customers during the prospective |
20 | calendar year, which fixed charge may be different by rate class in order to reasonably and equitably |
21 | spread the program costs across all customer classes. The fixed rate shall stay in effect until changed |
22 | after the first reconciliation filing set forth below and the rate reconciliation process shall be |
23 | repeated annually, as set forth below. The commission, in its discretion, may move the |
24 | reconciliation of costs and credits under § 39-26.1-5(f) into this reconciliation in order to have one |
25 | reconciliation of all program costs and credits from the long-term contracting standard, distributed- |
26 | generation standard contracting, and renewable energy growth program. |
27 | (b) Within three (3) months after the end of each program year, the electric distribution |
28 | company shall file a report with the public utilities commission that reconciles the total amount |
29 | recovered from distribution customers against the total of net payments and costs for the prior |
30 | program year for review and approval. |
31 | 39-26.6-26. Shared solar facilities. |
32 | (a) In order to facilitate the adoption of solar by customers in multifamily structures, |
33 | campuses, multi-structure business parks, multi-tenant or multi-owner commercial facilities, and |
34 | public entities with multiple accounts, the electric distribution company may establish rules and |
| LC002551 - Page 21 of 24 |
1 | tariffs for program years starting on or after April 1, 2016. The rules and tariffs will set forth the |
2 | requirements for eligible recipients, credit transfers, consumer protection, and other considerations |
3 | and terms, with input from the office, for the commission’s review and approval. |
4 | (b) Shared solar facilities will receive the same ceiling price and enroll from the same |
5 | classes of other projects of the same size and ownership as established by the board for a given |
6 | program year. |
7 | (c) All customer accounts receiving bill credits shall be in the same customer class and the |
8 | bill credit value from the shared solar facility shall be determined by the recipients’ rate class and |
9 | not that of the facility owner. The credit value shall be the distribution, transition, transmission, and |
10 | standard-offer supply rates of the bill credit recipients. |
11 | (d) Any value of bill credits not transferred from the shared solar facility shall be included |
12 | in the total performance-based incentive, which shall be paid in accordance with the tariffs |
13 | established by the electric distribution company. |
14 | 39-26.6-27. Community remote distributed generation system. |
15 | (a) In order to facilitate the adoption of participation in renewable energy projects by |
16 | eligible customers, the board may allocate a portion of the annual MW goal to a separate class, or |
17 | classes, of community remote distributed-generation systems, which may compete under separate |
18 | ceiling prices from non-community remote distributed-generation systems, for program years |
19 | starting on or after April 1, 2016. |
20 | (b) Upon such allocation by the board, the electric distribution company shall establish |
21 | rules and tariffs for program years starting on or after April 1, 2016, which rules and tariffs will set |
22 | forth the requirements for eligible recipients, credit transfers, consumer protection, and other |
23 | considerations and terms, with input from the office, for the commission’s review and approval. |
24 | (c) The value of credits to be allocated to credit recipients may be a fixed rate provided by |
25 | the system owner, but shall not be greater than the sum of the standard-offer service, less the |
26 | renewable energy standard charge or credit, and the transmission and transition rates, of the credit |
27 | recipient as offered by the electric distribution company in effect at the time of establishing the |
28 | transfer. If a fixed credit rate is not provided, the default credit will be the sum of the standard-offer |
29 | service, less the renewable energy standard charge or credit, and the transmission and transition |
30 | rates, of the credit recipient as offered by the electric distribution company in effect at the time of |
31 | the transfer. |
32 | (d) Any credits not allocated in any month will be valued at the then-current default credit |
33 | rate, and deducted from the total performance-based incentive of the enrolled system. |
34 | (e) Community remote distributed-generation systems shall not: |
| LC002551 - Page 22 of 24 |
1 | (1) Comprise more than thirty percent (30%) of the annual total of capacity available under |
2 | the renewable energy growth program in each year; |
3 | (2) Be subject to a ceiling price that is more than fifteen percent (15%) higher than the |
4 | then-in-effect ceiling price for the same technology of the same size as recommended by the board |
5 | and approved by the commission; or |
6 | (3) Transfer credits to any account in an amount that in KWh exceeds the prior three-year |
7 | (3) annual average usage. |
8 | SECTION 2. This act shall take effect on January 1, 2026. |
======== | |
LC002551 | |
======== | |
| LC002551 - Page 23 of 24 |
EXPLANATION | |
BY THE LEGISLATIVE COUNCIL | |
OF | |
A N A C T | |
RELATING TO PUBLIC UTILITIES AND CARRIERS -- THE RENEWABLE ENERGY | |
GROWTH PROGRAM | |
*** | |
1 | This act would repeal the Renewable Energy Growth Program. |
2 | This act would take effect on January 1, 2026. |
======== | |
LC002551 | |
======== | |
| LC002551 - Page 24 of 24 |