It is enacted by the General Assembly as follows: | |
1 | SECTION 1. Title 45 of the General Laws entitled "TOWNS AND CITIES" is hereby |
2 | amended by adding thereto the following chapter: |
3 | CHAPTER 53.1 |
4 | TIVERTON'S NEW CONSTRUCTION PROJECTS ACT |
5 | 45-53.1-1. Title. |
6 | This chapter shall be known and may be cited as the "Tiverton's New Construction Projects |
7 | Act." |
8 | 45-53.1-2. Definitions. |
9 | For the purposes of this chapter, the following words and terms shall have the following |
10 | meanings: |
11 | (1) "Bonus units" means additional residential units approved by the town of Tiverton as |
12 | part of a development project in accordance with the town's zoning and development policies. |
13 | (2) "Building permit" means a permit issued by the town of Tiverton granting authorization |
14 | for the commencement of construction on a project. |
15 | (3) "Certificate of occupancy" means a certificate issued by the town of Tiverton |
16 | confirming that a building has been completed in compliance with all building codes and is safe |
17 | for occupancy. |
18 | (5) "Preliminary approval" means the initial approval granted to a development project |
| |
1 | after review and recommendation by the appropriate municipal authority. |
2 | (4) "Final approval" means the final authorization given by the town of Tiverton following |
3 | successful completion of all necessary review and approval processes for a development project. |
4 | 45-53.1-3. Timelines for approval and permitting. |
5 | (a) In the town of Tiverton, the period between the granting of preliminary approval and |
6 | the granting of final approval for a development project shall not exceed one year. |
7 | (b) In the town of Tiverton, the period between the granting of final approval and the |
8 | issuance of a building permit shall not exceed two (2) years. |
9 | (c) In the town of Tiverton, if the applicant does not request a building permit within the |
10 | two (2) year period following final approval, the application and vesting shall be considered void. |
11 | The development process shall need to be restarted, and the applicant will need to resubmit a new |
12 | application for review and approval. |
13 | 45-53.1-4. Temporary addition of units to town's total unit count. |
14 | (a) In the town of Tiverton, once an applicant requests a building permit, the number of |
15 | units approved for the development, including any bonus units, shall be temporarily added to the |
16 | total unit count. This count shall be included in the town of Tiverton's current housing inventory. |
17 | (b) The units, including bonus units, shall be permanently added to the town of Tiverton's |
18 | unit count upon the issuance of a certificate of occupancy for the development or three (3) years |
19 | from the date of the request for a building permit, whichever occurs first. |
20 | (c) The town of Tiverton shall be allowed to count the units, including bonus units, against |
21 | other new developments while the construction is ongoing. This shall ensure that the town of |
22 | Tiverton remains in compliance with its housing and development goals, while still providing |
23 | flexibility to the applicant during the construction phase. |
24 | SECTION 2. This act shall take effect upon passage. |
======== | |
LC002696 | |
======== | |
| LC002696 - Page 2 of 3 |
EXPLANATION | |
BY THE LEGISLATIVE COUNCIL | |
OF | |
A N A C T | |
RELATING TO TOWNS AND CITIES -- TIVERTON'S NEW CONSTRUCTION PROJECTS | |
ACT | |
*** | |
1 | This act would set timelines for Tiverton's new construction, including one year for final |
2 | approval, two (2) years for building permits, and temporary inclusion of units in the town's count |
3 | until completion or three (3) years, whichever comes first. |
4 | This act would take effect upon passage. |
======== | |