It is enacted by the General Assembly as follows: | |
1 | SECTION 1. Section 42-11.1-3 of the General Laws in Chapter 42-11.1 entitled "Prompt |
2 | Payment by Department of Administration" is hereby amended to read as follows: |
3 | 42-11.1-3. Time period for payment. |
4 | (a) All bills shall be paid within thirty (30) working calendar days of receipt of a proper |
5 | invoice or other contractual dates for periodic payments, except when a contractor has failed to |
6 | submit a bill in accordance with contractually imposed time frames. |
7 | (b) Each contractor shall make payment to subcontractors within ten (10) calendar days of |
8 | receipt of payment by the state; provided, however, that the contractor may setoff a payment due |
9 | to a subcontractor by an amount equal to the amount of an unpaid legally enforceable debt owed |
10 | by the subcontractor to the contractor or any amount which the contractor is entitled to withhold |
11 | under the terms of the contract entered into by the contractor and subcontractor, or any amount |
12 | owed by the subcontractor to the contractor by way of a statutory obligation, or enforceable lien, |
13 | of which the contractor or subcontractor had previous knowledge or notice, or has reason to believe |
14 | exists. |
15 | (c) Each subcontractor shall make payments to its lower tier subcontractors within five (5) |
16 | calendar days of receipt of payment by the prime contractor. |
17 | (c)(d) This section shall not apply to contractors or subcontractors performing work |
18 | pursuant to a contract awarded by the department of transportation unless the subcontractor |
| |
1 | provides a payment and performance bond in an amount equal to the contract between the |
2 | contractor and subcontractor. |
3 | (e) The state shall pay a deposit to prime contractors in a sufficient period prior to the |
4 | commencement of the scope of work of a minority business enterprise (MBE), as defined in § 37- |
5 | 14.1-3, subcontractors solely for the purpose of the prime contractor making prearranged scheduled |
6 | payments, pursuant to a written contract between the prime contractor and MBE subcontractors, to |
7 | MBE subcontractors for the scope of the MBE subcontractors' work. Upon receipt of the deposit, |
8 | the prime contractor shall pay the MBE subcontractors within five (5) calendar days, pursuant to |
9 | the prearranged scheduled payments based upon percentage of work completed. Upon failure of |
10 | the prime contractor to timely pay the MBE subcontractors, the state shall pay the MBE |
11 | subcontractors directly and seek reimbursement from the prime contractor with any administrative |
12 | costs incurred by the state. This payment schedule shall be attached as an exhibit to the prime |
13 | contractor contract and approved by the state. |
14 | (f) The director of the department of administration shall adopt regulations in accordance |
15 | with chapter 35 of title 42, the ("administrative procedures act") which are consistent with this |
16 | chapter and chapter 2 of title 37, ("the state purchases act") governing the prompt payment by |
17 | contractors to subcontractors and in the instance of payments to MBE subcontractors, deposits to |
18 | contractors to allow weekly payments to MBE subcontractors. |
19 | SECTION 2. Chapter 42-11.1 of the General Laws entitled "Prompt Payment by |
20 | Department of Administration" is hereby amended by adding thereto the following section: |
21 | 42-11.1-17. Disqualification from contract award. |
22 | (a) No contract as defined in § 42-11.1-2, shall be awarded to any contractor currently in |
23 | violation of the provisions of this chapter. |
24 | (b) Prior to the awarding of any contract as defined in § 42-11.1-2, the contractor shall |
25 | certify under oath, that the contractor has fully satisfied and paid all subcontractors for all work |
26 | previously provided by the subcontractors pursuant to any subcontract with the contractor, and |
27 | additionally shall, if requested, provide evidence satisfactory to the director of the department of |
28 | administration that the contractor has fully satisfied and paid all subcontractors for all work |
29 | previously provided by the subcontractors pursuant to any subcontract with the contractor. |
30 | SECTION 3. This act shall take effect upon passage. |
======== | |
LC000048 | |
======== | |
| LC000048 - Page 2 of 3 |
EXPLANATION | |
BY THE LEGISLATIVE COUNCIL | |
OF | |
A N A C T | |
RELATING TO STATE AFFAIRS AND GOVERNMENT -- PROMPT PAYMENT BY | |
DEPARTMENT OF ADMINISTRATION--SUBCONTRACTOR PAYMENTS | |
*** | |
1 | This act would help expedite the payments made to subcontractors for work they perform |
2 | on state contracts. It would also establish a new process to help minority business enterprises collect |
3 | for their work on state contracts from their prime contractors. This act would further require that |
4 | contractors certify, and if requested provide evidence that all subcontractors have been paid for |
5 | previous subcontracting work prior to the award of a state contract. |
6 | This act would take effect upon passage. |
======== | |