2012 -- S 2395 SUBSTITUTE A | |
|
======= | |
|
LC01555/SUB A | |
|
======= | |
|
STATE OF RHODE ISLAND | |
|
| |
|
IN GENERAL ASSEMBLY | |
|
| |
|
JANUARY SESSION, A.D. 2012 | |
|
| |
|
____________ | |
|
| |
|
A N A C T | |
|
RELATING TO HEALTH AND SAFETY - REFUSE DISPOSAL | |
|
|
      |
|
|
      |
|
     Introduced By: Senators Lombardo, Lanzi, Cote, Picard, and Sheehan | |
|
     Date Introduced: February 15, 2012 | |
|
     Referred To: Senate Environment & Agriculture | |
|
It is enacted by the General Assembly as follows: | |
|
1-1 |
     SECTION 1. Section 23-18.9-14 of the General Laws in Chapter 23-18.9 entitled "Refuse |
|
1-2 |
Disposal" is hereby amended to read as follows: |
|
1-3 |
     23-18.9-14. Testing and analysis of air and water -- Environmental management |
|
1-4 |
district.-- (a) Applicability. - This section applies to all solid waste management |
|
1-5 |
facilities/activities regulated pursuant to this chapter that are undertaken within and in the vicinity |
|
1-6 |
of an area known as the environmental management district, located in the town of Johnston and |
|
1-7 |
the city of Cranston; the district is bounded by Plainfield Pike on the south; Peck Hill Road on the |
|
1-8 |
west; Central Avenue on the north; and I-295 on the east. |
|
1-9 |
      (b) On-site monitoring. |
|
1-10 |
      (1) The director of the department of environmental management (DEM), in consultation |
|
1-11 |
with the director of the department of health (DOH), is authorized to promulgate any rules and |
|
1-12 |
regulations that are necessary to require the development and implementation of onsite ambient |
|
1-13 |
air and water monitoring plans for all facilities/activities covered by this section. The regulations |
|
1-14 |
shall be promulgated no later than December 31, 2000, and shall be subject to the Administrative |
|
1-15 |
Procedures Act, chapter 35 of title 42. These regulations shall, at a minimum, provide for the |
|
1-16 |
following: |
|
1-17 |
      (i) Define the minimum criteria that shall require the development and implementation |
|
1-18 |
of an onsite ambient air and water monitoring plan; |
|
1-19 |
      (ii) Establish the time period that a facility/activity shall have to initially prepare an |
|
1-20 |
onsite ambient air and water monitoring plan and submit it to DEM for review; |
|
2-1 |
      (iii) Define the minimum content that shall be included in an onsite ambient air and |
|
2-2 |
water monitoring plan; |
|
2-3 |
      (iv) Establish the criteria that DEM shall use for review and approval of an onsite |
|
2-4 |
ambient air and water monitoring plan; |
|
2-5 |
      (v) Establish the criteria that DEM shall use for determining how long an approved |
|
2-6 |
onsite ambient air and water monitoring plan must remain in effect and the criteria for |
|
2-7 |
termination of an approved onsite ambient air and water monitoring plan; and |
|
2-8 |
      (vi) Define the process for public involvement in the development and review of onsite |
|
2-9 |
ambient air and water monitoring plans. |
|
2-10 |
      (2) The facility shall implement the outside ambient air and water monitoring plan within |
|
2-11 |
thirty (30) days of DEM approval. Data collected under onsite ambient air and water monitoring |
|
2-12 |
plans shall be evaluated by both DEM and DOH. DOH shall provide a written evaluation of this |
|
2-13 |
data to the host community(s), the facility(s), any oversight council or organization that focuses |
|
2-14 |
on the environmental management district, and any members of the public who request the |
|
2-15 |
evaluation. |
|
2-16 |
      (3) Should a facility not abide by the newly promulgated rules and regulations requiring |
|
2-17 |
a party to conduct an onsite ambient air and water monitoring plan, the director shall take |
|
2-18 |
enforcement action to compel those activities. The director may, at his or her discretion, prepare |
|
2-19 |
and implement an onsite ambient air and water monitoring plan for facilities that do not comply |
|
2-20 |
with the order. The facility shall be responsible to reimburse DEM for all costs, including interest, |
|
2-21 |
incurred in developing and implementing a plan. |
|
2-22 |
      (c) Offsite monitoring. - (1) If, upon the evaluation of data provided pursuant to |
|
2-23 |
subsection (b), the DEM and DOH directors jointly determine that any facility/activity is causing |
|
2-24 |
emissions of air or water pollutants at levels that could cause adverse health impacts, create |
|
2-25 |
objectionable or nuisance odors, or otherwise adversely impact human health or the environment, |
|
2-26 |
either individually or in conjunction with other sources in the surrounding community(s), the |
|
2-27 |
DEM director, in consultation with the DOH director, is authorized to require the |
|
2-28 |
facility(s)/activity(s) to develop and implement offsite ambient air and/or water monitoring plans |
|
2-29 |
within the environmental management district. Regulations governing the development and |
|
2-30 |
implementation of these offsite plans shall be promulgated in conjunction with, and subject to the |
|
2-31 |
same provisions as those authorized under subsection (b). |
|
2-32 |
      (2) Any facility subject to the offsite monitoring requirement shall implement the offsite |
|
2-33 |
ambient air and/or water monitoring plan within thirty (30) days of DEM approval. Data collected |
|
2-34 |
under offsite ambient air and/or water monitoring plans shall be evaluated by both DEM and |
|
3-1 |
DOH. DOH shall provide a written evaluation of this data to the host community(s), the |
|
3-2 |
facility(s), any oversight council or organization that focuses on the environmental management |
|
3-3 |
district, and any members of the public who request the evaluation. |
|
3-4 |
      (3) Should a facility not abide by the newly promulgated rules and regulations requiring |
|
3-5 |
a party to conduct an offsite ambient air and/or water monitoring plan, the director shall take |
|
3-6 |
enforcement action to compel those activities. The director may, at his or her discretion, prepare |
|
3-7 |
and implement an offsite ambient air and/or water monitoring plan for facilities that do not |
|
3-8 |
comply with the order. That facility shall be responsible to reimburse DEM for all costs, |
|
3-9 |
including interest, incurred in developing and implementing a plan. |
|
3-10 |
     (d) Ambient monitoring. In addition to any off-site monitoring required pursuant to |
|
3-11 |
subsection (c) above, Rhode Island Resource Recovery Corporation shall establish and operate an |
|
3-12 |
off-site ambient air monitoring network consisting of not less than four (4) monitoring locations, |
|
3-13 |
three (3) of which shall be located in Johnston and one of which shall be located in Cranston. The |
|
3-14 |
objective of the monitoring network shall be to continuously monitor ambient air for the presence |
|
3-15 |
of odorous contaminants from landfill gas. Wind speed and wind direction shall also be recorded |
|
3-16 |
continuously at the monitoring locations. The locations of said monitors shall be determined by |
|
3-17 |
the department of environmental management, in consultation with the host community of the |
|
3-18 |
subject monitor. The contaminants of concern to be monitored and the methodology of |
|
3-19 |
monitoring shall be determined by the department of environmental management, in consultation |
|
3-20 |
with the department of health. Results from monitoring shall be submitted to the department of |
|
3-21 |
environmental management, the department of health, the town of Johnston, the city of Cranston, |
|
3-22 |
and posted on a publicly accessible page on the Rhode Island Resource Recovery Corporation |
|
3-23 |
website for reference by the public. All costs of purchasing, installing, and operating the |
|
3-24 |
monitoring network shall be paid by Rhode Island Resource Recovery Corporation. |
|
3-25 |
     SECTION 2. Ambient monitoring pursuant to the act shall continue until December 31, |
|
3-26 |
2022. The director of the department of environmental management and the director of the |
|
3-27 |
department of health shall report an evaluation of all data collected pursuant to this act to the |
|
3-28 |
general assembly on or before December 31, 2020. After evaluation of data provided pursuant to |
|
3-29 |
section 23-18.9-14.1, if the director of the department of environmental management and the |
|
3-30 |
director of the department of health jointly determine that any facility/activity is causing |
|
3-31 |
emissions of air or water pollutants at levels that could cause adverse health impacts, have created |
|
3-32 |
objectionable or nuisance odors, or otherwise have adversely impacted human health or the |
|
3-33 |
environment, either individually or in conjunction with other sources in the surrounding |
|
3-34 |
community(ies), then the director of the department of environmental management, in |
|
4-1 |
consultation with the director the department of health is authorized to require the |
|
4-2 |
facility(ies)/activity(ies) to maintain ambient monitoring until December 31, 2032 or until said |
|
4-3 |
evaluation of data shows that such facility(ies)/activity(ies) would not impact human health or |
|
4-4 |
environment as stated herein. |
|
4-5 |
     SECTION 3. This act shall take effect upon passage. |
|
      | |
|
======= | |
|
LC01555/SUB A | |
|
======== | |
|
EXPLANATION | |
|
BY THE LEGISLATIVE COUNCIL | |
|
OF | |
|
A N A C T | |
|
RELATING TO HEALTH AND SAFETY - REFUSE DISPOSAL | |
|
*** | |
|
5-1 |
     This act would require the Rhode Island Resource Recovery Corporation to establish an |
|
5-2 |
off-site air quality monitoring system. |
|
5-3 |
     This act would take effect upon passage. |
|
      | |
|
======= | |
|
LC01555/SUB A | |
|
======= |