Chapter 190
2025 -- H 5687 SUBSTITUTE A
Enacted 06/26/2025

A N   A C T
RELATING TO STATE AFFAIRS AND GOVERNMENT -- ENERGY FACILITY SITING ACT

Introduced By: Representatives Dawson, Kazarian, Furtado, and Boylan

Date Introduced: February 26, 2025

It is enacted by the General Assembly as follows:
     SECTION 1. Section 42-98-1.1 of the General Laws in Chapter 42-98 entitled "Energy
Facility Siting Act" is hereby amended to read as follows:
     42-98-1.1. Capital city underground utility initiative.
     (a) Legislative Findings
     (1) In 2004, the cities of Providence and East Providence exercised their rights under this
section as it was originally enacted in 2004, to forego receipt of a customer credit owed to the
Narragansett Electric Company’s (“company”) electric customers residing in those communities,
opting instead to use those communities’ allocated share of the customer credit to fund a portion of
the cost of constructing the “Underground Alignment” of a portion of the E-183 115 kilovolt
electric transmission line as defined in the Settlement Agreement approved by the Board on May
28, 2004 in Docket No. SB-2003-01.
     (2) The Settlement Agreement approved by the Board in Docket No. SB-2003-01 provided,
in part, that the parties to the Settlement Agreement would work to reach an agreement on a route
for the Underground Alignment while the Rhode Island attorney general would work to secure
funding for construction of the Underground Alignment. The Settlement Agreement provided
further that if the Underground Alignment was found not to be feasible for reasons including cost
or constructability, other identified alignments of the relevant portion of the E-183 electric
transmission line would be considered in order of preference.
     (3) On January 17, 2018, the Board issued an Order determining that the Underground
Alignment and the “Bridge Alignment North,” as defined in the Settlement Agreement, were not
feasible, and approving construction of the “Bridge Alignment South,” as defined in the Settlement
Agreement.
     (4) Following appellate review pursuant to § 42-98-12, on June 17, 2022, in Case No. 2018-
40-M.P., the Supreme Court of Rhode Island upheld the Board’s January 17, 2018 Order.
     (5) Due to the foregoing events and decisions, as of 2025, no portion of the E-183
transmission line has been constructed underground and no part of the customer credit referred to
in subsection (a)(1) of this section has been returned to electric customers in the cities of Providence
and East Providence.
     (6) The customer credit that arose from the company’s base distribution rate case in 2004,
which the cities of Providence and East Providence did not accept on behalf of their ratepayers, has
been segregated and has accrued interest for the benefit of Providence and East Providence electric
distribution customers.
     (7) The cities of Providence and East Providence desire to have portions of the E-183
electric transmission line located underground and require legislative authorization for funding
mechanisms to pay the incremental cost, over and above the estimated cost of the Bridge Alignment
South, of the burial of portions of the E-183 electric transmission line along the southern shore of
Fox and India Points that are south of Interstate 195 and in East Providence on the east side of the
Seekonk River (the “Bridge Alignment South – Hybrid”).
     (b) The public utilities commission shall permit the city of Providence or and the city of
East Providence, upon petition by a duly authorized representative of such municipality, to forego
some or apply all of the respective municipality’s pro rata share of the refund accruing to the
ratepayers of the respective municipality as computed under section 11(c) of the 3rd Third
Amended Settlement Agreement in Docket No. 2930; provided, however, that the city council of
each petitioning ratifies such action by passage of a resolution.
     (b) The public utilities commission shall permit, upon petition by the attorney general, for
the use of up to two million dollars ($2,000,000) from Narragansett Electric Company’s Storm
Contingency Fund for purposes of under grounding that portion of the E-183 transmission line
under consideration in Energy Facility Siting Board Docket 2003-01.
     (c) Narragansett Electric Company shall be required to apply to the regional grid operator
or its successor organization for approval to charge New England regional network service
customers for the capital costs associated with the construction of Phase II overhead configuration
labeled the “North Bridge Alignment” as defined by the Settlement Agreement that was approved
by the Energy Facility Siting Board in Docket 2003-1.
     (d) The Narragansett Electric Company (“company”) shall be authorized to proceed with
the construction of the underground alignment of the E-183 line referenced in the Settlement
Agreement that was approved by the Energy Facility Siting Board in Docket 2003-01
(“Underground alignment”), including the acquisition of any property rights needed to implement
the underground alignment, plus accrued interest, toward the incremental cost of constructing the
Bridge Alignment South - Hybrid.
     (c) The Company shall apply to the regional grid operator or its successor organization for
approval to charge New England regional network service customers for the capital costs associated
with undergrounding portions of the E-183 transmission line as described herein and as verified for
feasibility by the Narragansett Electric Company. Any Portion of costs not categorized as eligible
for regional cost allocation shall be governed by subsections (d) through (f) of this section and
remain chargeable to the electric customers of Providence and East Providence.
     (d) Notwithstanding the Supreme Court’s June 17, 2022, affirmation of the Board’s
January 17, 2018 Order, the Board shall have jurisdiction to consider a modification to the license
to include burial of a portion of the E-183 electric transmission line without having to consider
whether the requirements of §§ 42-98-11(b)(1) and (b)(2) have been met. Following approval by
the Board of a modified license, the company shall be authorized to proceed with the construction
of the modification which will include consideration of the Bridge Alignment South-Hybrid,
subject to the passage of resolutions by both city councils of the cities of Providence and East
Providence agreeing that any incremental costs above existing funding made available pursuant to
subsection (b) of this section may be included in electric rates of electric customers in those cities.
Such resolutions must be delivered to the public utilities commission no later than July 1, 2009.
Notwithstanding the terms of the Settlement, to 2026. To the extent the actual costs for the
underground alignment Bridge Alignment South - Hybrid exceed the funding obtained for the
project pursuant to this section and from federal and any other sources, the company is authorized
to include the incremental costs above those funding levels in its distribution rate base and reflect
the revenue requirement, including interest, any resulting tax adjustments, and billing system
modification costs in rates charged to the electric distribution customers within the cities of
Providence and East Providence in a manner approved by the public utilities commission, subject
to the timely passage and delivery of the resolution resolutions specified above. Such rate
adjustment shall be made within six (6) months from project completion, applying the same
ratemaking principles as ordinarily applied to distribution capital projects when they are allowed
in its distribution rate base by the public utilities commission. After completion of the underground
alignment, the public utilities commission shall conduct a review of costs incurred to construct the
underground alignment in order to verify that the company’s calculation and implementation of
rates are in compliance with this section; provided, further, the auditor general shall perform a
performance audit of state costs. billed as a per kilowatt hour charge designed to recover the full
incremental cost of the Bridge Alignment South – Hybrid, including interest, any resulting tax
adjustments, and billing system modification costs, over a period not less than three (3) years
subject to reconciliation of the final cost compared to billed revenues. The incremental costs of
undergrounding net of the customer credit referenced in subsection (b) of this section will be
allocated to each city based on the actual cost of the underground portions in each respective city.
The company shall book the revenues collected through the rate adjustment for such incremental
underground construction costs as contribution in aid of construction in the appropriate
transmission accounts.
     (e) If the cities of Providence and East Providence obtain any other source of funding that
can be used to offset the cost of burial of the E-183 electric transmission line, that source of funding
shall offset the amount of the rate adjustment charged to the electric ratepayers in the cities of
Providence and/or East Providence under subsection (c) of this section as defined by the source of
funding.
     (e)(f) If the underground alignment goes forward, the company shall retain such portions
of the properties acquired to implement the underground alignment as may be necessary and
prudent, and shall transfer any remaining portions of said properties to the redevelopment authority
of the city in which the property is located after the completion of the project, at the city’s request
and at no additional cost to the city conditions precedent to the construction of the Bridge
Alignment South - Hybrid are satisfied, the cities of Providence and East Providence shall acquire
and convey to the company, all easements or property rights needed in the company’s reasonable
judgment for the construction, operation, and maintenance of the relevant segment of E-183. Any
costs associated with the transfer of property rights will be included in the overall project costs and
allocated as described in subsection (d) of this section. Any property and easements no longer being
used by the company for utility purposes after the underground alignment Bridge Alignment South-
Hybrid is completed also shall be transferred to the city in which such property is located after the
completion of the project, at the city’s request and at no additional cost to the city. If there is any
dispute about the extent to which property or easements are needed and therefore should not be
transferred, the public utilities commission shall decide the issue upon petition by the affected city.
     SECTION 2. This act shall take effect upon passage.
========
LC001794/SUB A/2
========