Chapter 190 |
2025 -- H 5687 SUBSTITUTE A Enacted 06/26/2025 |
A N A C T |
RELATING TO STATE AFFAIRS AND GOVERNMENT -- ENERGY FACILITY SITING ACT |
Introduced By: Representatives Dawson, Kazarian, Furtado, and Boylan |
Date Introduced: February 26, 2025 |
It is enacted by the General Assembly as follows: |
SECTION 1. Section 42-98-1.1 of the General Laws in Chapter 42-98 entitled "Energy |
Facility Siting Act" is hereby amended to read as follows: |
42-98-1.1. Capital city underground utility initiative. |
(a) Legislative Findings |
(1) In 2004, the cities of Providence and East Providence exercised their rights under this |
section as it was originally enacted in 2004, to forego receipt of a customer credit owed to the |
Narragansett Electric Company’s (“company”) electric customers residing in those communities, |
opting instead to use those communities’ allocated share of the customer credit to fund a portion of |
the cost of constructing the “Underground Alignment” of a portion of the E-183 115 kilovolt |
electric transmission line as defined in the Settlement Agreement approved by the Board on May |
28, 2004 in Docket No. SB-2003-01. |
(2) The Settlement Agreement approved by the Board in Docket No. SB-2003-01 provided, |
in part, that the parties to the Settlement Agreement would work to reach an agreement on a route |
for the Underground Alignment while the Rhode Island attorney general would work to secure |
funding for construction of the Underground Alignment. The Settlement Agreement provided |
further that if the Underground Alignment was found not to be feasible for reasons including cost |
or constructability, other identified alignments of the relevant portion of the E-183 electric |
transmission line would be considered in order of preference. |
(3) On January 17, 2018, the Board issued an Order determining that the Underground |
Alignment and the “Bridge Alignment North,” as defined in the Settlement Agreement, were not |
feasible, and approving construction of the “Bridge Alignment South,” as defined in the Settlement |
Agreement. |
(4) Following appellate review pursuant to § 42-98-12, on June 17, 2022, in Case No. 2018- |
40-M.P., the Supreme Court of Rhode Island upheld the Board’s January 17, 2018 Order. |
(5) Due to the foregoing events and decisions, as of 2025, no portion of the E-183 |
transmission line has been constructed underground and no part of the customer credit referred to |
in subsection (a)(1) of this section has been returned to electric customers in the cities of Providence |
and East Providence. |
(6) The customer credit that arose from the company’s base distribution rate case in 2004, |
which the cities of Providence and East Providence did not accept on behalf of their ratepayers, has |
been segregated and has accrued interest for the benefit of Providence and East Providence electric |
distribution customers. |
(7) The cities of Providence and East Providence desire to have portions of the E-183 |
electric transmission line located underground and require legislative authorization for funding |
mechanisms to pay the incremental cost, over and above the estimated cost of the Bridge Alignment |
South, of the burial of portions of the E-183 electric transmission line along the southern shore of |
Fox and India Points that are south of Interstate 195 and in East Providence on the east side of the |
Seekonk River (the “Bridge Alignment South – Hybrid”). |
(b) The public utilities commission shall permit the city of Providence or and the city of |
East Providence, upon petition by a duly authorized representative of such municipality, to forego |
some or apply all of the respective municipality’s pro rata share of the refund accruing to the |
ratepayers of the respective municipality as computed under section 11(c) of the 3rd Third |
Amended Settlement Agreement in Docket No. 2930; provided, however, that the city council of |
each petitioning ratifies such action by passage of a resolution. |
(b) The public utilities commission shall permit, upon petition by the attorney general, for |
the use of up to two million dollars ($2,000,000) from Narragansett Electric Company’s Storm |
Contingency Fund for purposes of under grounding that portion of the E-183 transmission line |
under consideration in Energy Facility Siting Board Docket 2003-01. |
(c) Narragansett Electric Company shall be required to apply to the regional grid operator |
or its successor organization for approval to charge New England regional network service |
customers for the capital costs associated with the construction of Phase II overhead configuration |
labeled the “North Bridge Alignment” as defined by the Settlement Agreement that was approved |
by the Energy Facility Siting Board in Docket 2003-1. |
(d) The Narragansett Electric Company (“company”) shall be authorized to proceed with |
the construction of the underground alignment of the E-183 line referenced in the Settlement |
Agreement that was approved by the Energy Facility Siting Board in Docket 2003-01 |
(“Underground alignment”), including the acquisition of any property rights needed to implement |
the underground alignment, plus accrued interest, toward the incremental cost of constructing the |
Bridge Alignment South - Hybrid. |
(c) The Company shall apply to the regional grid operator or its successor organization for |
approval to charge New England regional network service customers for the capital costs associated |
with undergrounding portions of the E-183 transmission line as described herein and as verified for |
feasibility by the Narragansett Electric Company. Any Portion of costs not categorized as eligible |
for regional cost allocation shall be governed by subsections (d) through (f) of this section and |
remain chargeable to the electric customers of Providence and East Providence. |
(d) Notwithstanding the Supreme Court’s June 17, 2022, affirmation of the Board’s |
January 17, 2018 Order, the Board shall have jurisdiction to consider a modification to the license |
to include burial of a portion of the E-183 electric transmission line without having to consider |
whether the requirements of §§ 42-98-11(b)(1) and (b)(2) have been met. Following approval by |
the Board of a modified license, the company shall be authorized to proceed with the construction |
of the modification which will include consideration of the Bridge Alignment South-Hybrid, |
subject to the passage of resolutions by both city councils of the cities of Providence and East |
Providence agreeing that any incremental costs above existing funding made available pursuant to |
subsection (b) of this section may be included in electric rates of electric customers in those cities. |
Such resolutions must be delivered to the public utilities commission no later than July 1, 2009. |
Notwithstanding the terms of the Settlement, to 2026. To the extent the actual costs for the |
underground alignment Bridge Alignment South - Hybrid exceed the funding obtained for the |
project pursuant to this section and from federal and any other sources, the company is authorized |
to include the incremental costs above those funding levels in its distribution rate base and reflect |
the revenue requirement, including interest, any resulting tax adjustments, and billing system |
modification costs in rates charged to the electric distribution customers within the cities of |
Providence and East Providence in a manner approved by the public utilities commission, subject |
to the timely passage and delivery of the resolution resolutions specified above. Such rate |
adjustment shall be made within six (6) months from project completion, applying the same |
ratemaking principles as ordinarily applied to distribution capital projects when they are allowed |
in its distribution rate base by the public utilities commission. After completion of the underground |
alignment, the public utilities commission shall conduct a review of costs incurred to construct the |
underground alignment in order to verify that the company’s calculation and implementation of |
rates are in compliance with this section; provided, further, the auditor general shall perform a |
performance audit of state costs. billed as a per kilowatt hour charge designed to recover the full |
incremental cost of the Bridge Alignment South – Hybrid, including interest, any resulting tax |
adjustments, and billing system modification costs, over a period not less than three (3) years |
subject to reconciliation of the final cost compared to billed revenues. The incremental costs of |
undergrounding net of the customer credit referenced in subsection (b) of this section will be |
allocated to each city based on the actual cost of the underground portions in each respective city. |
The company shall book the revenues collected through the rate adjustment for such incremental |
underground construction costs as contribution in aid of construction in the appropriate |
transmission accounts. |
(e) If the cities of Providence and East Providence obtain any other source of funding that |
can be used to offset the cost of burial of the E-183 electric transmission line, that source of funding |
shall offset the amount of the rate adjustment charged to the electric ratepayers in the cities of |
Providence and/or East Providence under subsection (c) of this section as defined by the source of |
funding. |
(e)(f) If the underground alignment goes forward, the company shall retain such portions |
of the properties acquired to implement the underground alignment as may be necessary and |
prudent, and shall transfer any remaining portions of said properties to the redevelopment authority |
of the city in which the property is located after the completion of the project, at the city’s request |
and at no additional cost to the city conditions precedent to the construction of the Bridge |
Alignment South - Hybrid are satisfied, the cities of Providence and East Providence shall acquire |
and convey to the company, all easements or property rights needed in the company’s reasonable |
judgment for the construction, operation, and maintenance of the relevant segment of E-183. Any |
costs associated with the transfer of property rights will be included in the overall project costs and |
allocated as described in subsection (d) of this section. Any property and easements no longer being |
used by the company for utility purposes after the underground alignment Bridge Alignment South- |
Hybrid is completed also shall be transferred to the city in which such property is located after the |
completion of the project, at the city’s request and at no additional cost to the city. If there is any |
dispute about the extent to which property or easements are needed and therefore should not be |
transferred, the public utilities commission shall decide the issue upon petition by the affected city. |
SECTION 2. This act shall take effect upon passage. |
======== |
LC001794/SUB A/2 |
======== |