|
|
======= |
ARTICLE 6 |
RELATING TO DEBT MANAGEMENT ACT JOINT RESOLUTION
|
SECTION 1. This article consists of joint resolutions that is submitted pursuant to Rhode |
Island General Law ยง 35-18-1, et seq. |
SECTION 2. Confined Aquatic Dredged Material Disposal Cells. |
WHEREAS, over the past year the Army Corps of Engineers has approached the Ccoastal |
Rresources Mmanagement Ccouncil to act as the local sponsor to the federal action of maintaining |
the depths of the Providence River and Harbor Shipping Channel; and |
WHEREAS, the Providence River and Shipping Channel was last maintained in 2003; and |
WHEREAS, the project will include dredging and removal of sediments not suitable for |
ocean disposal, and thus will require the construction of a new Confined Aquatic Disposal (CAD) |
Cell to dispose and sequester those sediments; and |
WHEREAS, CAD cells are constructed in aquatic environments to reduce the |
environmental risk from sediments not suitable for ocean disposal by storing these sediments in a |
depression in the bottom of the aquatic system; and |
WHEREAS, CAD cells offer a major economic value, as a significant cost of disposing |
dredged materials is in the transportation of the dredged material to a disposal location; and |
WHEREAS, having CAD cells located within hundreds of feet from a dredging operation |
saves local port operators millions of dollars over the 10 ten-year (10) life of those cells; and |
WHERAS, the Ccoastal Rresources Mmanagement Ccouncil seeks to build additional |
capacity in the CAD Cells beyond that required only for this specific project, in order to account |
for the many port, maritime, and marina facilities that also have the need to dredge material at their |
facilities, which may not be suitable for ocean disposal, thereby saving these entities significant |
cost, in both sediment testing and transportation of the material to other locations, due to the fact |
that the existing CAD cells in the river have reached their useful ten-year design life; and |
WHEREAS, with the approval by the voters of the 2016 Rhode Island Port Infrastructure |
Bond referendum, the need to maintain the viability of port and maritime operations, the state's |
marine trades industry, and the increase economic value of ProvPort, increased disposal capacities |
from new CAD cells are needed; and |
WHEREAS, the Army Corps of Engineers expects to begin maintenance of the Providence |
River and Harbor Shipping Channel in the fall of 2018, the total cost share of the local sponsor are |
required by the end of FY 2018; and |
WHEREAS, the project is considered a federal maintenance project, the Sstate is required |
to pay for the creation of the CAD cell only at an up-front cost share of thirty five percent (35%); |
and |
WHEREAS, the project costs associated with this project is estimated to be eleven million |
dollars ($11.0 million), with five hundred thousand dollars ($500,000) derived from the Ccoastal |
Rresources Mmanagement Ccouncil Ddredge Ffund. The total financing obligation of the Sstate |
of Rhode Island would be approximately ten million five hundred thousand dollars ($10.5 million), |
with ten million four hundred thousand dollars ($10.4 million) deposited in the project fund and |
one hundred thousand dollars ($100,000) allocated to pay the associated costs of financing. Total |
payments on the Sstate's obligation over ten (10) years on the ten million five hundred thousand |
dollars ($10.5 million) issuance are projected to be thirteen million six hundred thousand dollars |
($13.6 million) assuming an average interest rate of five percent (5.0%). A minimum of five million |
dollars ($5.0 million) of the total principal and interest payments shall be financed from an increase |
in fees charged to marine operators to deposit their dredged materials into CAD cells, with general |
revenue appropriations used to supplement fee revenues. General revenue appropriations shall |
finance principal and interest payments in any fiscal year that fee revenues are insufficient; now, |
therefore, be it |
RESOLVED, that this Ggeneral Aassembly hereby approves financing in an amount not |
to exceed ten million five hundred thousand dollars ($10.5 million) for the provision of funds for |
the Confined Aquatic Disposal Cells project, including one hundred thousand dollars ($100,000) |
to pay costs of financing. |
SECTION 3. Energy Performance Contract โ University of Rhode Island โ Phase 3 |
WHEREAS, the Ccouncil on Ppostsecondary Eeducation and the Uuniversity of Rhode |
Island, herby referred to as "the Uuniversity," are proposing projects that involve the |
implementation of professionally guided capital investments in energy efficiency improvements to |
Uuniversity buildings and infrastructure that will pay for themselves through cost avoidance, while |
reducing long-term energy consumption associated with operations; and |
WHEREAS, the Uuniversity presently manages over three hundred twenty four (324) |
buildings, with associated utility infrastructure, containing over four million eight hundred fifty |
thousand (4,850,000) square feet of space, a majority of which was constructed over thirty years |
ago. Energy efficiency has become a vital feature of the institution's fiscal responsibility; and |
WHEREAS, energy performance contracting has been significantly enhanced and refined, |
and many examples exist of programs successfully employed around the country that are prudent |
from both a fiscal management and an environmental stewardship perspective; and |
WHEREAS, various private sector companies, hereinafter referred to as energy service |
companies or "ESCOs", are willing to guarantee the performance of the improvements yielding |
energy savings to pay for the cost of the replacement of antiquated and inefficient equipment, |
including boilers, heating and air conditioning, lighting and other building systems and equipment; |
and |
WHEREAS, the higher education system has successfully participated with the state |
department of administration in a request for proposal process to enter into an energy performance |
contract with ESCO to provide investment grade energy audit evaluations, design, installation, and |
maintenance services, as well as assistance in securing rebate resources and the guarantee of the |
energy or water saving performance of the installed retrofit measures; and |
WHEREAS, the evaluations of an energy service company further affirms the significant |
opportunity to implement energy conservation improvements on a building-by-building basis that |
pay for themselves through operating budget savings within a fifteen-year (15) period; and |
WHEREAS, tax exempt financing via "certificates of participation," with associated debt |
service supported for the financing term by energy cost avoidance (i.e., by redirecting dollars that |
would have paid for utility consumption, but with the improvements can be redeployed to repay |
the financing) is the most cost effective means of supporting the investment in energy efficiency |
improvements under this program; and |
WHEREAS, the Uuniversity is seeking to undertake energy performance contracts to |
replace obsolete equipment with new equipment and infrastructure components employing high |
energy efficient technologies, to employ insulation and weatherization measures, and to deploy |
measures that sustain the highest performance levels for these improvements; and |
WHEREAS, the estimated cost of such contracts are for the Uuniversity, an amount not to |
exceed eleven million six hundred thousand dollars ($11.6 million), with the request to the state to |
have with ten million five hundred thousand dollars ($10.5 million) deposited into the construction |
fund, six hundred ninety-six thousand dollars ($696,000) deposited in a capitalized interest fund, |
and four hundred thirty thousand dollars ($430,000) to pay associated costs of financing. Total |
payments on the state's obligation over fifteen (15) years on the eleven million six hundred thousand |
dollars ($11.6 million) issuance are projected to be sixteen million eight hundred thousand dollars |
($16.8 million), assuming an average effective interest rate of five percent (5.0%), the payments |
would be derived by the Uuniversity from energy savings; now, therefore, be it |
RESOLVED, that the Uuniversity is authorized to proceed with the aforementioned |
projects in the amounts specified above; and be it further |
RESOLVED, that these contracts will be structured so that, at a minimum, the annual |
principal, interest and service and maintenance costs resulting from these contracts would be fully |
offset by the cumulative annual energy savings derived from energy efficiency improvements, the |
performance of which being guaranteed by the ESCOs; and be it further |
RESOLVED, that these contracts would be multi-year contracts of up to a term of fifteen |
(15) years. In addition to saving energy and helping to protect the Uuniversity from future energy |
cost increases, these contracts would aid in reducing maintenance costs by providing new, efficient |
equipment and technology that outperforms older higher energy consuming systems; and be it |
further |
RESOLVED, that this joint resolution shall take effect immediately upon its passage. |
SECTION 4. White Horn Brook Apartments โ University of Rhode Island. |
WHEREAS, the Rhode Island Ccouncil on Ppostsecondary Eeducation is proposing a |
project which that involves the construction of a new residence hall on the west bank of the White |
Horn Brook located in the northwest corner of the Kingston campus of the Uuniversity of Rhode |
Island in the Ttown of South Kingstown, Rhode Island; and |
WHEREAS, the growth of undergraduate student enrollment is critical to the fiscal health |
of the Uuniversity; and |
WHEREAS, there is high undergraduate student demand for apartment-style, on-campus |
housing; and |
WHEREAS, the Uuniversity is committed to providing adequate and appropriate housing |
opportunities for its students; and |
WHEREAS, the Uuniversity continues to undertake significant improvements to existing |
dormitory-style housing facilities and has built new units that offer both suite style and apartment |
living options with the goal of providing over fifty percent (50%) of its undergraduate students on |
campus housing in keeping with its peer institutions; and |
WHEREAS, apartment-style housing units are critical for the on-campus retention of third- |
and fourth-year students that often seek alternative housing off campus; and |
WHEREAS, a recent market study has demonstrated that the market demand for additional, |
apartment-style campus housing indicates that this project will be fully occupied upon completion |
and into the future; and |
WHEREAS, the Rhode Island Public Corporation Debt Management Act requires the |
Ggeneral Aassembly to provide its consent to the issuance or incurring by the Sstate of Rhode |
Island and other public agencies of certain obligations including financing guarantees or other |
agreements; and |
WHEREAS, the design and construction of the project will be financed through Rhode |
Island Health and Educational Building (RIHEBC) revenue bonds, with an expected term of thirty |
(30) years; and |
WHEREAS, the total project costs associated with the completion of the project and |
proposed financing method would be supported approximately ninety-five percent (95%) by |
auxiliary fee revenues for URI Hhousing and Rresidential Llife for the apartment building and |
approximately five percent (5%) by Uuniversity general funds for site enabling facility relocation, |
utility and hardscape and landscape infrastructure and site work; and |
WHEREAS, the project is currently in design and targeting a total project financing cost |
of eighty eight million seven hundred and eighty seven thousand dollars ($88,787,000) in RIHEBC |
bonds, with a request to have seventy eight million four hundred forty thousand dollars |
($78,440,000) deposited into a construction fund, eight million thirty seven thousand dollars |
($8,037,000) deposited in a capitalized interest fund, and two million three hundred ten thousand |
dollars ($2,310,000) to pay associated cost of financing, and with an assumed interest rate of five |
percent (5%) debt service repayments will not exceed one hundred seventy three million two |
hundred seventy one thousand and six hundred fifty three dollars ($173,271,653); and |
WHEREAS, the Uuniversity has been advised by its architectural and project management |
firms to anticipate potential additional escalation of construction costs leading up to the final |
pricing of the construction of this project; now, therefore, be it |
RESOLVED, that the Ggeneral Aassembly hereby approves financing in an amount not to |
exceed total debt service payments of one hundred seventy three million two hundred seventy one |
thousand and six hundred fifty three dollars ($173,271,653) for construction of a new, apartment- |
style residence facility on the Uuniversity of Rhode Island Kingston Ccampus, with the not-to- |
exceed amount to be financed determined by the actual financing interest rate at the time of the |
bond issuance; and be it further |
RESOLVED, that this joint resolution shall take effect immediately upon its passage. |
SECTION 5. This resolution shall apply to financing obligations issued within four (4) |
years of the date of passage of this resolution. |
SECTION 6. This article shall take effect upon passage. |