=======
art.006/3/006/2/016/1
=======
ARTICLE 6
RELATING TO DEBT MANAGEMENT ACT JOINT RESOLUTION

     SECTION 1. This article consists of joint resolutions that is submitted pursuant to Rhode
Island General Law ยง 35-18-1, et seq.
     SECTION 2. Confined Aquatic Dredged Material Disposal Cells.
     WHEREAS, over the past year the Army Corps of Engineers has approached the Ccoastal
Rresources Mmanagement Ccouncil to act as the local sponsor to the federal action of maintaining
the depths of the Providence River and Harbor Shipping Channel; and
     WHEREAS, the Providence River and Shipping Channel was last maintained in 2003; and
     WHEREAS, the project will include dredging and removal of sediments not suitable for
ocean disposal, and thus will require the construction of a new Confined Aquatic Disposal (CAD)
Cell to dispose and sequester those sediments; and
     WHEREAS, CAD cells are constructed in aquatic environments to reduce the
environmental risk from sediments not suitable for ocean disposal by storing these sediments in a
depression in the bottom of the aquatic system; and
     WHEREAS, CAD cells offer a major economic value, as a significant cost of disposing
dredged materials is in the transportation of the dredged material to a disposal location; and
     WHEREAS, having CAD cells located within hundreds of feet from a dredging operation
saves local port operators millions of dollars over the 10 ten-year (10) life of those cells; and
     WHERAS, the Ccoastal Rresources Mmanagement Ccouncil seeks to build additional
capacity in the CAD Cells beyond that required only for this specific project, in order to account
for the many port, maritime, and marina facilities that also have the need to dredge material at their
facilities, which may not be suitable for ocean disposal, thereby saving these entities significant
cost, in both sediment testing and transportation of the material to other locations, due to the fact
that the existing CAD cells in the river have reached their useful ten-year design life; and
     WHEREAS, with the approval by the voters of the 2016 Rhode Island Port Infrastructure
Bond referendum, the need to maintain the viability of port and maritime operations, the state's
marine trades industry, and the increase economic value of ProvPort, increased disposal capacities
from new CAD cells are needed; and
     WHEREAS, the Army Corps of Engineers expects to begin maintenance of the Providence
River and Harbor Shipping Channel in the fall of 2018, the total cost share of the local sponsor are
required by the end of FY 2018; and
     WHEREAS, the project is considered a federal maintenance project, the Sstate is required
to pay for the creation of the CAD cell only at an up-front cost share of thirty five percent (35%);
and
     WHEREAS, the project costs associated with this project is estimated to be eleven million
dollars ($11.0 million), with five hundred thousand dollars ($500,000) derived from the Ccoastal
Rresources Mmanagement Ccouncil Ddredge Ffund. The total financing obligation of the Sstate
of Rhode Island would be approximately ten million five hundred thousand dollars ($10.5 million),
with ten million four hundred thousand dollars ($10.4 million) deposited in the project fund and
one hundred thousand dollars ($100,000) allocated to pay the associated costs of financing. Total
payments on the Sstate's obligation over ten (10) years on the ten million five hundred thousand
dollars ($10.5 million) issuance are projected to be thirteen million six hundred thousand dollars
($13.6 million) assuming an average interest rate of five percent (5.0%). A minimum of five million
dollars ($5.0 million) of the total principal and interest payments shall be financed from an increase
in fees charged to marine operators to deposit their dredged materials into CAD cells, with general
revenue appropriations used to supplement fee revenues. General revenue appropriations shall
finance principal and interest payments in any fiscal year that fee revenues are insufficient; now,
therefore, be it
     RESOLVED, that this Ggeneral Aassembly hereby approves financing in an amount not
to exceed ten million five hundred thousand dollars ($10.5 million) for the provision of funds for
the Confined Aquatic Disposal Cells project, including one hundred thousand dollars ($100,000)
to pay costs of financing.
     SECTION 3. Energy Performance Contract โ€“ University of Rhode Island โ€“ Phase 3
     WHEREAS, the Ccouncil on Ppostsecondary Eeducation and the Uuniversity of Rhode
Island, herby referred to as "the Uuniversity," are proposing projects that involve the
implementation of professionally guided capital investments in energy efficiency improvements to
Uuniversity buildings and infrastructure that will pay for themselves through cost avoidance, while
reducing long-term energy consumption associated with operations; and
     WHEREAS, the Uuniversity presently manages over three hundred twenty four (324)
buildings, with associated utility infrastructure, containing over four million eight hundred fifty
thousand (4,850,000) square feet of space, a majority of which was constructed over thirty years
ago. Energy efficiency has become a vital feature of the institution's fiscal responsibility; and
     WHEREAS, energy performance contracting has been significantly enhanced and refined,
and many examples exist of programs successfully employed around the country that are prudent
from both a fiscal management and an environmental stewardship perspective; and
     WHEREAS, various private sector companies, hereinafter referred to as energy service
companies or "ESCOs", are willing to guarantee the performance of the improvements yielding
energy savings to pay for the cost of the replacement of antiquated and inefficient equipment,
including boilers, heating and air conditioning, lighting and other building systems and equipment;
and
     WHEREAS, the higher education system has successfully participated with the state
department of administration in a request for proposal process to enter into an energy performance
contract with ESCO to provide investment grade energy audit evaluations, design, installation, and
maintenance services, as well as assistance in securing rebate resources and the guarantee of the
energy or water saving performance of the installed retrofit measures; and
     WHEREAS, the evaluations of an energy service company further affirms the significant
opportunity to implement energy conservation improvements on a building-by-building basis that
pay for themselves through operating budget savings within a fifteen-year (15) period; and
     WHEREAS, tax exempt financing via "certificates of participation," with associated debt
service supported for the financing term by energy cost avoidance (i.e., by redirecting dollars that
would have paid for utility consumption, but with the improvements can be redeployed to repay
the financing) is the most cost effective means of supporting the investment in energy efficiency
improvements under this program; and
     WHEREAS, the Uuniversity is seeking to undertake energy performance contracts to
replace obsolete equipment with new equipment and infrastructure components employing high
energy efficient technologies, to employ insulation and weatherization measures, and to deploy
measures that sustain the highest performance levels for these improvements; and
     WHEREAS, the estimated cost of such contracts are for the Uuniversity, an amount not to
exceed eleven million six hundred thousand dollars ($11.6 million), with the request to the state to
have with ten million five hundred thousand dollars ($10.5 million) deposited into the construction
fund, six hundred ninety-six thousand dollars ($696,000) deposited in a capitalized interest fund,
and four hundred thirty thousand dollars ($430,000) to pay associated costs of financing. Total
payments on the state's obligation over fifteen (15) years on the eleven million six hundred thousand
dollars ($11.6 million) issuance are projected to be sixteen million eight hundred thousand dollars
($16.8 million), assuming an average effective interest rate of five percent (5.0%), the payments
would be derived by the Uuniversity from energy savings; now, therefore, be it
     RESOLVED, that the Uuniversity is authorized to proceed with the aforementioned
projects in the amounts specified above; and be it further
     RESOLVED, that these contracts will be structured so that, at a minimum, the annual
principal, interest and service and maintenance costs resulting from these contracts would be fully
offset by the cumulative annual energy savings derived from energy efficiency improvements, the
performance of which being guaranteed by the ESCOs; and be it further
     RESOLVED, that these contracts would be multi-year contracts of up to a term of fifteen
(15) years. In addition to saving energy and helping to protect the Uuniversity from future energy
cost increases, these contracts would aid in reducing maintenance costs by providing new, efficient
equipment and technology that outperforms older higher energy consuming systems; and be it
further
     RESOLVED, that this joint resolution shall take effect immediately upon its passage.
     SECTION 4. White Horn Brook Apartments โ€“ University of Rhode Island.
     WHEREAS, the Rhode Island Ccouncil on Ppostsecondary Eeducation is proposing a
project which that involves the construction of a new residence hall on the west bank of the White
Horn Brook located in the northwest corner of the Kingston campus of the Uuniversity of Rhode
Island in the Ttown of South Kingstown, Rhode Island; and
     WHEREAS, the growth of undergraduate student enrollment is critical to the fiscal health
of the Uuniversity; and
     WHEREAS, there is high undergraduate student demand for apartment-style, on-campus
housing; and
     WHEREAS, the Uuniversity is committed to providing adequate and appropriate housing
opportunities for its students; and
     WHEREAS, the Uuniversity continues to undertake significant improvements to existing
dormitory-style housing facilities and has built new units that offer both suite style and apartment
living options with the goal of providing over fifty percent (50%) of its undergraduate students on
campus housing in keeping with its peer institutions; and
     WHEREAS, apartment-style housing units are critical for the on-campus retention of third-
and fourth-year students that often seek alternative housing off campus; and
     WHEREAS, a recent market study has demonstrated that the market demand for additional,
apartment-style campus housing indicates that this project will be fully occupied upon completion
and into the future; and
     WHEREAS, the Rhode Island Public Corporation Debt Management Act requires the
Ggeneral Aassembly to provide its consent to the issuance or incurring by the Sstate of Rhode
Island and other public agencies of certain obligations including financing guarantees or other
agreements; and
     WHEREAS, the design and construction of the project will be financed through Rhode
Island Health and Educational Building (RIHEBC) revenue bonds, with an expected term of thirty
(30) years; and
     WHEREAS, the total project costs associated with the completion of the project and
proposed financing method would be supported approximately ninety-five percent (95%) by
auxiliary fee revenues for URI Hhousing and Rresidential Llife for the apartment building and
approximately five percent (5%) by Uuniversity general funds for site enabling facility relocation,
utility and hardscape and landscape infrastructure and site work; and
     WHEREAS, the project is currently in design and targeting a total project financing cost
of eighty eight million seven hundred and eighty seven thousand dollars ($88,787,000) in RIHEBC
bonds, with a request to have seventy eight million four hundred forty thousand dollars
($78,440,000) deposited into a construction fund, eight million thirty seven thousand dollars
($8,037,000) deposited in a capitalized interest fund, and two million three hundred ten thousand
dollars ($2,310,000) to pay associated cost of financing, and with an assumed interest rate of five
percent (5%) debt service repayments will not exceed one hundred seventy three million two
hundred seventy one thousand and six hundred fifty three dollars ($173,271,653); and
     WHEREAS, the Uuniversity has been advised by its architectural and project management
firms to anticipate potential additional escalation of construction costs leading up to the final
pricing of the construction of this project; now, therefore, be it
     RESOLVED, that the Ggeneral Aassembly hereby approves financing in an amount not to
exceed total debt service payments of one hundred seventy three million two hundred seventy one
thousand and six hundred fifty three dollars ($173,271,653) for construction of a new, apartment-
style residence facility on the Uuniversity of Rhode Island Kingston Ccampus, with the not-to-
exceed amount to be financed determined by the actual financing interest rate at the time of the
bond issuance; and be it further
     RESOLVED, that this joint resolution shall take effect immediately upon its passage.
     SECTION 5. This resolution shall apply to financing obligations issued within four (4)
years of the date of passage of this resolution.
     SECTION 6. This article shall take effect upon passage.