Chapter 176 |
2017 -- H 5483 SUBSTITUTE B Enacted 06/30/2017 |
A N A C T |
RELATING TO PUBLIC UTILITIES AND CARRIERS |
Introduced By: Representatives Marshall, Regunberg, Ruggiero, McKiernan, and |
Date Introduced: February 15, 2017 |
It is enacted by the General Assembly as follows: |
SECTION 1. Section 39-26.3-2 of the General Laws in Chapter 39-26.3 entitled |
"Distributed Generation Interconnection" is hereby amended to read as follows: |
39-26.3-2. Definitions. |
The following terms shall have the meanings given below for purposes of this chapter: |
(1) "Applicant" means an electric distribution customer or distributed-generation |
developer who submits an application to the electric distribution company for the installation of a |
renewable, distributed-generation interconnection to the distribution system for a renewable, |
distributed-generation project that, as contemplated, meets the eligibility requirements for net |
metering contained within title 39 or the eligibility requirements for a standard contract contained |
within title 39. |
(2)(4) "Impact study" means an engineering study that includes an estimate of the cost of |
interconnecting to the distribution system that would be assessed on the applicant for an |
interconnection that is based on an engineering study of the details of the proposed generation |
project. Such estimate generally will have a probability of accuracy of plus or minus twenty five |
percent (25%). Such an estimate may be relied upon by the applicant for purposes of determining |
the expected cost of interconnection, but the distribution company may not be held liable or |
responsible if the actual costs exceed the estimate as long as the estimate was provided in good |
faith and the interconnection was implemented prudently by the electric distribution company. |
(3)(5) "Impact study fee" means a fee that shall be charged to the applicant to obtain an |
impact study as specified in § 39-26.2-4 39-26.3-4 of this chapter. |
(4)(2) "Feasibility study" means a high-level project assessment that includes an estimate |
of the cost of interconnecting to the distribution system that would be assessed on the applicant |
for an interconnection. Such estimate is not based on any engineering study, but is based on past |
experience and judgment of the electric distribution company, taking into account the information |
in the application, the location of the interconnection, and general knowledge of the distribution |
and transmission system. Such estimate cannot be relied upon by the applicant for purposes of |
holding the electric distribution company liable or responsible for its accuracy as long as the |
electric distribution company has provided the estimate in good faith. The feasibility study |
estimate shall be a range within which the electric distribution company believes the |
interconnection costs are likely to be and shall include a disclaimer that explains the nature of the |
estimate. |
(5)(3) "Feasibility study fee" means a fee that shall be charged to the applicant to obtain a |
feasibility study as specified in § 39-26.2-4 39-26.3-4 of this chapter. |
(6) "Renewable energy resource" means those resources set forth in §39-26-5. |
SECTION 2. Chapter 39-26.3 of the General Laws entitled "Distributed Generation |
Interconnection" is hereby amended by adding thereto the following section: |
39-26.3-4.1. Interconnection standards. |
(a) The electric distribution company may only charge an interconnecting, renewable- |
energy customer for any system modifications to its electric power system specifically necessary |
for and directly related to the interconnection. |
(b) If the public utilities commission determines that a specific system modification |
benefiting other customers has been accelerated due to an interconnection request, it may order |
the interconnecting customer to fund the modification subject to repayment of the depreciated |
value of the modification as of the time the modification would have been necessary as |
determined by the public utilities commission. Any system modifications benefiting other |
customers shall be included in rates as determined by the public utilities commission. |
(c) If an interconnecting, renewable-energy customer is required to pay for system |
modifications and a subsequent renewable-energy or commercial customer relies on those |
modifications to connect to the distribution system within ten (10) years of the earlier |
interconnecting, renewable-energy customer's payment, the subsequent customer will make a |
prorated contribution toward the cost of the system modifications which that will be credited to |
the earlier interconnecting, renewable-energy customer as determined by the public utilities |
commission. |
(d) An electric distribution company shall acknowledge to the interconnecting, |
renewable-energy customer receipt of an application to initiate the interconnection process within |
three (3) business days of receipt. The electric distribution company shall notify the |
interconnecting, renewable-energy customer in writing within ten (10) business days of receipt |
that the application is or is not complete and, if not, advise what is missing. Any disputes |
regarding whether and when an application to initiate the interconnection process is complete |
shall be resolved expeditiously at the public utilities commission. The maximum time allowed |
between the date of the completed application and delivery of an executable interconnection |
service agreement shall be one hundred seventy-five (175) calendar days or two hundred (200) |
calendar days if a detailed study is required. All electric distribution company system |
modifications must be completed by the date which is the later of: (1) No longer than two |
hundred seventy (270) calendar days, or three hundred sixty (360) calendar days if substation |
work is necessary, from the date of the electric distribution company's receipt of the |
interconnecting, renewable-energy customer's executed interconnection services agreement; or |
(2) The interconnecting, renewable-energy customer's agreed upon extension of the time between |
the execution of the interconnection services agreement and interconnection as set forth in |
writing. All deadlines herein are subject to all payments being made in accordance with the |
distributed generation interconnection tariff on file with the public utilities commission and the |
interconnection services agreement. These system modification deadlines cannot be extended due |
to customer delays in providing required information, all of which must be requested and |
obtained before completion of the impact study. The deadlines for completion of system |
modifications will be extended only to the extent of events that are clearly not under the control |
of the electric distribution company, such as extended prohibitive weather, union work stoppage |
or force majeure, or third-party delays, including, without limitation, delays due to ISO-NE |
requirements not attributable to electric distribution company actions, and which cannot be |
resolved despite commercially reasonable efforts. The electric distribution company shall notify |
the customer of the start of any claimed deadline extension as soon as practicable, its cause and |
when it concludes, all in writing. Any actual damages that a court of competent jurisdiction |
orders the electric distribution company to pay to an interconnecting, renewable-energy customer |
as a direct result of the electric distribution company's failure to comply with the requirements of |
this subsection shall be payable by its shareholders and may not be recovered from customers, |
provided that the total amount of damages awarded for any and all such claims shall not exceed, |
in the aggregate, an amount equal to the amount of the incentive the electric distribution company |
would have earned as provided for in §§39-26.6-12(j)(3) and 39-26.1-4 in the year in which the |
system modifications were required to be completed. In no event shall the electric distribution |
company be liable to the interconnecting, renewable-energy customer for any indirect, incidental, |
special, consequential, or punitive damages of any kind whatsoever as a result of the electric |
distribution company's failure to comply with this section. |
(e) On or before September 1, 2017, the public utilities commission shall initiate a docket |
to establish metrics for the electric distribution company's performance in meeting the time |
frames set forth herein and in the distributed generation interconnection standards approved by |
the public utilities commission. The public utilities commission may include incentives and |
penalties in the performance metrics. |
(f) The proposed interconnection of any new renewable energy resource that replaces the |
same existing renewable energy resource of the same or less nameplate capacity that has been in |
operation in the twelve (12) months preceding notification of such replacement shall be subject to |
a sixty-(60) day (60) review. The purpose of such sixty-(60) day (60) review is to allow the |
electric distribution company to determine whether any system modifications are required to |
support the interconnection of the replacement renewable energy resource. If there is a need for |
system modifications because of an interconnection policy change implemented by the electric |
distribution company, then the system modification may be included in rates as determined by the |
public utilities commission. If there is a need for system modifications only because of a change |
in the rating or utility disturbance response that adversely affects the impact of the facility on the |
distribution system, then the interconnecting, renewable-energy customer shall be responsible for |
the cost of the system modifications. |
SECTION 3. This act shall take effect upon passage. |
======== |
LC000960/SUB B |
======== |