| Chapter 176 |
| 2017 -- H 5483 SUBSTITUTE B Enacted 06/30/2017 |
| A N A C T |
| RELATING TO PUBLIC UTILITIES AND CARRIERS |
| Introduced By: Representatives Marshall, Regunberg, Ruggiero, McKiernan, and |
| Date Introduced: February 15, 2017 |
| It is enacted by the General Assembly as follows: |
| SECTION 1. Section 39-26.3-2 of the General Laws in Chapter 39-26.3 entitled |
| "Distributed Generation Interconnection" is hereby amended to read as follows: |
| 39-26.3-2. Definitions. |
| The following terms shall have the meanings given below for purposes of this chapter: |
| (1) "Applicant" means an electric distribution customer or distributed-generation |
| developer who submits an application to the electric distribution company for the installation of a |
| renewable, distributed-generation interconnection to the distribution system for a renewable, |
| distributed-generation project that, as contemplated, meets the eligibility requirements for net |
| metering contained within title 39 or the eligibility requirements for a standard contract contained |
| within title 39. |
| (2)(4) "Impact study" means an engineering study that includes an estimate of the cost of |
| interconnecting to the distribution system that would be assessed on the applicant for an |
| interconnection that is based on an engineering study of the details of the proposed generation |
| project. Such estimate generally will have a probability of accuracy of plus or minus twenty five |
| percent (25%). Such an estimate may be relied upon by the applicant for purposes of determining |
| the expected cost of interconnection, but the distribution company may not be held liable or |
| responsible if the actual costs exceed the estimate as long as the estimate was provided in good |
| faith and the interconnection was implemented prudently by the electric distribution company. |
| (3)(5) "Impact study fee" means a fee that shall be charged to the applicant to obtain an |
| impact study as specified in § 39-26.2-4 39-26.3-4 of this chapter. |
| (4)(2) "Feasibility study" means a high-level project assessment that includes an estimate |
| of the cost of interconnecting to the distribution system that would be assessed on the applicant |
| for an interconnection. Such estimate is not based on any engineering study, but is based on past |
| experience and judgment of the electric distribution company, taking into account the information |
| in the application, the location of the interconnection, and general knowledge of the distribution |
| and transmission system. Such estimate cannot be relied upon by the applicant for purposes of |
| holding the electric distribution company liable or responsible for its accuracy as long as the |
| electric distribution company has provided the estimate in good faith. The feasibility study |
| estimate shall be a range within which the electric distribution company believes the |
| interconnection costs are likely to be and shall include a disclaimer that explains the nature of the |
| estimate. |
| (5)(3) "Feasibility study fee" means a fee that shall be charged to the applicant to obtain a |
| feasibility study as specified in § 39-26.2-4 39-26.3-4 of this chapter. |
| (6) "Renewable energy resource" means those resources set forth in §39-26-5. |
| SECTION 2. Chapter 39-26.3 of the General Laws entitled "Distributed Generation |
| Interconnection" is hereby amended by adding thereto the following section: |
| 39-26.3-4.1. Interconnection standards. |
| (a) The electric distribution company may only charge an interconnecting, renewable- |
| energy customer for any system modifications to its electric power system specifically necessary |
| for and directly related to the interconnection. |
| (b) If the public utilities commission determines that a specific system modification |
| benefiting other customers has been accelerated due to an interconnection request, it may order |
| the interconnecting customer to fund the modification subject to repayment of the depreciated |
| value of the modification as of the time the modification would have been necessary as |
| determined by the public utilities commission. Any system modifications benefiting other |
| customers shall be included in rates as determined by the public utilities commission. |
| (c) If an interconnecting, renewable-energy customer is required to pay for system |
| modifications and a subsequent renewable-energy or commercial customer relies on those |
| modifications to connect to the distribution system within ten (10) years of the earlier |
| interconnecting, renewable-energy customer's payment, the subsequent customer will make a |
| prorated contribution toward the cost of the system modifications which that will be credited to |
| the earlier interconnecting, renewable-energy customer as determined by the public utilities |
| commission. |
| (d) An electric distribution company shall acknowledge to the interconnecting, |
| renewable-energy customer receipt of an application to initiate the interconnection process within |
| three (3) business days of receipt. The electric distribution company shall notify the |
| interconnecting, renewable-energy customer in writing within ten (10) business days of receipt |
| that the application is or is not complete and, if not, advise what is missing. Any disputes |
| regarding whether and when an application to initiate the interconnection process is complete |
| shall be resolved expeditiously at the public utilities commission. The maximum time allowed |
| between the date of the completed application and delivery of an executable interconnection |
| service agreement shall be one hundred seventy-five (175) calendar days or two hundred (200) |
| calendar days if a detailed study is required. All electric distribution company system |
| modifications must be completed by the date which is the later of: (1) No longer than two |
| hundred seventy (270) calendar days, or three hundred sixty (360) calendar days if substation |
| work is necessary, from the date of the electric distribution company's receipt of the |
| interconnecting, renewable-energy customer's executed interconnection services agreement; or |
| (2) The interconnecting, renewable-energy customer's agreed upon extension of the time between |
| the execution of the interconnection services agreement and interconnection as set forth in |
| writing. All deadlines herein are subject to all payments being made in accordance with the |
| distributed generation interconnection tariff on file with the public utilities commission and the |
| interconnection services agreement. These system modification deadlines cannot be extended due |
| to customer delays in providing required information, all of which must be requested and |
| obtained before completion of the impact study. The deadlines for completion of system |
| modifications will be extended only to the extent of events that are clearly not under the control |
| of the electric distribution company, such as extended prohibitive weather, union work stoppage |
| or force majeure, or third-party delays, including, without limitation, delays due to ISO-NE |
| requirements not attributable to electric distribution company actions, and which cannot be |
| resolved despite commercially reasonable efforts. The electric distribution company shall notify |
| the customer of the start of any claimed deadline extension as soon as practicable, its cause and |
| when it concludes, all in writing. Any actual damages that a court of competent jurisdiction |
| orders the electric distribution company to pay to an interconnecting, renewable-energy customer |
| as a direct result of the electric distribution company's failure to comply with the requirements of |
| this subsection shall be payable by its shareholders and may not be recovered from customers, |
| provided that the total amount of damages awarded for any and all such claims shall not exceed, |
| in the aggregate, an amount equal to the amount of the incentive the electric distribution company |
| would have earned as provided for in §§39-26.6-12(j)(3) and 39-26.1-4 in the year in which the |
| system modifications were required to be completed. In no event shall the electric distribution |
| company be liable to the interconnecting, renewable-energy customer for any indirect, incidental, |
| special, consequential, or punitive damages of any kind whatsoever as a result of the electric |
| distribution company's failure to comply with this section. |
| (e) On or before September 1, 2017, the public utilities commission shall initiate a docket |
| to establish metrics for the electric distribution company's performance in meeting the time |
| frames set forth herein and in the distributed generation interconnection standards approved by |
| the public utilities commission. The public utilities commission may include incentives and |
| penalties in the performance metrics. |
| (f) The proposed interconnection of any new renewable energy resource that replaces the |
| same existing renewable energy resource of the same or less nameplate capacity that has been in |
| operation in the twelve (12) months preceding notification of such replacement shall be subject to |
| a sixty-(60) day (60) review. The purpose of such sixty-(60) day (60) review is to allow the |
| electric distribution company to determine whether any system modifications are required to |
| support the interconnection of the replacement renewable energy resource. If there is a need for |
| system modifications because of an interconnection policy change implemented by the electric |
| distribution company, then the system modification may be included in rates as determined by the |
| public utilities commission. If there is a need for system modifications only because of a change |
| in the rating or utility disturbance response that adversely affects the impact of the facility on the |
| distribution system, then the interconnecting, renewable-energy customer shall be responsible for |
| the cost of the system modifications. |
| SECTION 3. This act shall take effect upon passage. |
| ======== |
| LC000960/SUB B |
| ======== |