1

     SECTION 1. Section 16-7-40 of the General Laws in Chapter 16-7 entitled "Foundation

2

Level School Support [See Title 16 Chapter 97 - The Rhode Island Board of Education Act]" is

3

hereby amended to read as follows:

4

     16-7-40. Increased school housing ratio.

5

     (a)(1) In the case of regional school districts, the school housing aid ratio shall be increased

6

by two percent (2%) for each grade so consolidated.

7

     (2) Regional school districts undertaking renovation project(s) shall receive an increased

8

share ratio of four percent (4%) for those specific project(s) only, in addition to the combined share

9

ratio calculated in § 16-7-39 and this subsection.

10

     (3) Districts with free and reduced lunch student populations above twenty percent (20%)

11

will have their minimum housing aid share increased to forty percent (40%), in addition to the

12

combined share ratio calculated in § 16-7-39 and this subsection. This provision only applies to

13

projects that are completed after July 1, 2020.

14

     (b) In the case of projects undertaken by districts specifically for the purposes of school

15

safety and security, the school housing aid share ratio shall be increased by five percent (5%) for

16

these specific projects only, in the calculation of school housing aid. The increased share ratio shall

17

continue to be applied for as long as the project(s) receives state housing aid. In order to qualify for

18

the increased share ratio, seventy-five percent (75%) of the project costs must be specifically

 

1

directed to school safety and security measures. The council on elementary and secondary

2

education shall promulgate rules and regulations for the administration and operation of this

3

section.

4

     (c) For purposes of addressing health and safety deficiencies as defined by the school

5

building authority, including the remediation of hazardous materials, the school housing aid ratio

6

shall be increased by five percent (5%) so long as the construction of the project commences by

7

December 30, 2022, is completed by December 30, 2027, and a two hundred fifty million dollar

8

($250,000,000) general obligation bond is approved on the November 2018 ballot. In order to

9

qualify for the increased share ratio, twenty-five percent (25%) of the project costs or a minimum

10

of five hundred thousand dollars ($500,000) must be specifically directed to this purpose.

11

     (d) For purposes of educational enhancement, including projects devoted to the

12

enhancement of early childhood education and career and technical education, the school housing

13

aid ratio shall be increased by five percent (5%) so long as construction of the project commences

14

by December 30, 2022, is completed by December 30, 2027, and a two hundred fifty million dollar

15

($250,000,000) general obligation bond is approved on the November 2018 ballot. In order to

16

qualify for the increased share ratio, twenty-five percent (25%) of the project costs or a minimum

17

of five hundred thousand dollars ($500,000) must be specifically directed to these purposes.

18

     (e) For replacement of a facility that has a facilities condition index of sixty-five percent

19

(65%) or higher, the school housing ratio shall be increased by five percent (5%) so long as

20

construction of the project commences by December 30, 2023, is completed by December 30, 2028,

21

does not receive a bonus pursuant to subsection (f) or subsection (g), and a two hundred fifty million

22

dollar ($250,000,000) general obligation bond is approved on the November 2018 ballot. In order

23

to qualify for the increased share ratio, twenty-five percent (25%) of the project costs or a minimum

24

of five hundred thousand dollars ($500,000) must be specifically directed to this purpose.

25

     (f) For any new construction or renovation that increases the functional utilization of any

26

facility from less than sixty percent (60%) to more than eighty percent (80%), including the

27

consolidation of school buildings within or across districts, the school housing aid ratio shall be

28

increased by five percent (5%) so long as construction of the project commences by December 30,

29

2023, is completed by December 30, 2028, and a two hundred fifty million dollar ($250,000,000)

30

general obligation bond is approved on the November 2018 ballot. In order to qualify for the

31

increased share ratio, twenty-five percent (25%) of the project costs or a minimum of five hundred

32

thousand dollars ($500,000) must be specifically directed to this purpose.

33

     (g) For any new construction or renovation that decreases the functional utilization of any

34

facility from more than one hundred twenty percent (120%) to between eighty-five percent (85%)

 

LC003433 - Page 2 of 3

1

to one hundred five percent (105%), the school housing ratio shall be increased by five percent

2

(5%) so long as construction of the project commences by December 30, 2023, is completed by

3

December 30, 2028, and a two hundred fifty million dollar ($250,000,000) general obligation bond

4

is approved on the November 2018 ballot. In order to qualify for the increased share ratio, twenty-

5

five percent (25%) of the project costs or a minimum of five hundred thousand dollars ($500,000)

6

must be specifically directed to this purpose.

7

     (h) For consolidation of two (2) or more school buildings, within or across districts into

8

one school building, the school housing aid ratio shall be increased by five percent (5%) so long as

9

construction of the project commences by December 30, 2023, is completed by December 30, 2028,

10

a two hundred fifty million dollar ($250,000,000) general obligation bond is approved on the

11

November 2018 ballot, and does not receive a bonus pursuant to subsection (f) or subsection (g).

12

In order to qualify for the increased share ratio, twenty-five percent (25%) of the project costs or a

13

minimum of five hundred thousand dollars ($500,000) must be specifically directed to this purpose.

14

     (i) Any regionalized and/or non-regionalized school district receiving an increased share

15

ratio for a project approved prior to July 1, 2018, shall continue to receive the increased share ratio

16

for as long as the project receives state housing aid.

17

     SECTION 2. This act shall take effect upon passage.

========

LC003433

========

 

LC003433 - Page 3 of 3

EXPLANATION

BY THE LEGISLATIVE COUNCIL

OF

A N   A C T

RELATING TO EDUCATION -- FOUNDATION LEVEL SCHOOL SUPPORT [SEE TITLE

16 CHAPTER 97- THE RHODE ISLAND BOARD OF EDUCATION ACT]

***

1

     This act would provide that districts with free and reduced lunch populations above twenty

2

percent (20%) would have their minimum housing aid share increased to forty percent (40%) for

3

projects completed after July 1, 2020. It would also provide that the school housing aid ratio be

4

increased to five percent (5%) so long as the construction project is completed by December 30,

5

2027, whereas the prior provision would mandate that it commence by December 30, 2022.

6

     This act would take effect upon passage.

========

LC003433

========

 

LC003433 - Page 4 of 3